- (1) The public utility shall develop electricity supply resource procurement plans. The plans must be submitted to the commission at intervals determined in rules adopted by the commission.
- (2) An electricity supply resource procurement plan must demonstrate the public utility's achievement of the objectives provided in 69-8-419 and compliance with commission rules.
(3) The commission shall:
- (a) review the electricity supply resource procurement plan;
- (b) provide an opportunity to the public to comment on the plan in accordance with subsection (4); and
(c) issue written comments within 9 months after the plan is submitted to the commission that identify:
- (i) any concerns of the commission regarding the public utility's compliance with commission rules; and
- (ii) ways to remedy any concerns.
- (4) The commission shall hold two public meetings in an area of the state encompassed by the plan. Notice of the meetings must be published once a week for 2 consecutive weeks in a newspaper of general circulation at least 30 days prior to each meeting. (Repealed effective July 1, 2020--secs. 16, 20, Ch. 449, L. 2019.)
History: En. Sec. 2, Ch. 509, L. 2003; amd. Sec. 14, Ch. 491, L. 2007; amd. Sec. 1, Ch. 422, L. 2017.