(1) The following is the schedule of electrical inspection fees as charged by the department. As provided in ARM 24.301.203 local governments certified to enforce the electrical code may establish their own electrical permit fees.
Type of Installation Permit Fee
(a) single-family dwellings or cabins (includes attached garage if wired at the same time as the house or cabin). A cabin is a structure designed for use for overnight stays that may not meet the definition of a dwelling unit.
(b) private property accessory buildings (includes new service or upgrade of existing service for supply of power to garages, barns, sheds, etc.)
(c) multi-family dwellings (duplex through 12 units) per bldg*
(iv) 601 and up amp service 780
*Plus $60 per unit, up to and including 12 units.
*For buildings containing more than 12 units, use the commercial schedule that follows.
(d) multi-family dwellings (duplex through 12 units) rewire or remodel only - per dwelling unit
100
(e) single-family dwelling interior/exterior wiring/rewiring
(i) more than three circuits and change of service and/or interior panelboard
120
(ii) more than three circuits only (does not include change of service or panelboard)
100
(iv) one additional circuit or piece of equipment (hot tub, air conditioner, etc.)
45
(f) change of service
(g) modular homes, mobile homes, and recreational vehicles
(ii) wiring to a mobile, modular, or RV only on privately owned property
80
(ii) additional spaces over 3 spaces installed at the same time (per space)
5
(j) agricultural irrigation pumps or machines on a common surface
(o) Renewable energy system: net metering system or off-grid electrical generating system (photovoltaic (PV) system, wind generator, hydro turbine, etc.)
(p) all other installations (commercial, industrial, institutional, or for public use). Fees are based on total cost to the owner of all labor and materials to complete the electrical project. Electrical materials furnished by the owner must be included in the total electrical project cost:
| Cost of Electrical Installation | Fee |
| $0 - $1,000 | $45 for 1st $500 plus 6.0% of balance of construction cost |
| $1,001 - $10,000 | $75 for 1st $1,000 plus 2.0% of balance of construction cost |
| $10,001 - $50,000 | $255 for 1st $10,000 plus 0.5% of balance of construction cost |
| $50,001 or more | $455 for 1st $50,000 plus 0.3% of balance of construction cost |
Authorizing statute(s): 50-60-104, 50-60-203, 50-60-603, 50-60-604, MCA
Implementing statute(s): 50-60-104, 50-60-203, 50-60-603, 50-60-604, MCA
History: NEW, 1978 MAR p. 378, Eff. 3/25/78; AMD, 1978 MAR p. 1480, Eff. 10/27/78; AMD, 1979 MAR p. 1665, Eff. 12/28/79; AMD, 1981 MAR p. 1054, Eff. 9/18/81; TRANS, from Dept. of Admin., Ch. 352, L. 1985, Eff. 7/1/85; AMD, 1986 MAR p. 109, Eff. 1/31/86; AMD, 1987 MAR p. 2237, Eff. 12/11/87; AMD, 1994 MAR p. 670, Eff. 2/11/94; AMD, 1998 MAR p. 2563, Eff. 9/25/98; AMD, 1999 MAR p. 1885, Eff. 10/1/99; TRANS, from Commerce, & AMD, 2001 MAR p. 2293, Eff. 11/22/01; AMD, 2006 MAR p. 567, Eff. 2/24/06; AMD, 2010 MAR p. 1733, Eff. 7/30/10; AMD, 2014 MAR p. 2655, Eff. 10/24/14.