(1) An application for revision to a permit must be submitted for departmental review:
- (a) for any proposed change(s) in the operation as described in the original permit and subsequent revisions thereof; or
- (b) when required under ARM 17.24.414.
- (2) The operator may not implement the revision before obtaining the department's approval.
(3) An application for major revision:
- (a) must comply with subchapter 3, as appropriate;
- (b) is subject to the public notice and participation provisions of ARM 17.24.401 through 17.24.405; and
- (c) must include submittal of a new or updated probable hydrologic consequence determination, if determined necessary by the department for adequate permit review.
- (4) If impacts change, the department shall update the cumulative hydrologic impact assessment.
Authorizing statute(s): 82-4-205, MCA
Implementing statute(s): 82-4-221, MCA
History: NEW, 1980 MAR p. 725, Eff. 4/1/80; AMD, 1989 MAR p. 30, Eff. 1/13/89; TRANS, from DSL, 1996 MAR p. 2852; AMD, 1999 MAR p. 811, Eff. 4/23/99; AMD, 2024 MAR p. 255, Eff. 2/10/24.