Mo. Code Regs. Ann. tit. 7, § 10-24.140
Tradeoffs in Design-Build Contracting
Effective Jul 30, 2018sections 226.020, 226.030, and 227.107, RSMo 2016.* Original rule filed Aug. 15, 2005, effective Feb. 28, 2006. Amended: Filed Dec. 5, 2017, effective July 30, 2018Missouri Highways and Transportation Commission
PURPOSE: This rule describes when and 7 CSR 10-24
how tradeoffs should be used in awarding a design-build contract and documentation of the tradeoff decisions.
- (1) At its discretion, the commission may consider the tradeoff technique when it is desirable to award to other than the lowest priced proposer or other than the highest technically rated proposer.
(2) If the commission uses a tradeoff technique, the following is to be clearly stated in the solicitation:
- (A) All evaluation factors and significant subfactors that affect contract award and the factor’s relative importance; and
(B) Whether all evaluation factors other than cost or price, when combined, are—
- 1. Significantly more important than
cost or price; or
- 2. Approximately equal in importance to
cost or price; or
- 3. Significantly less important than cost
or price.
(3) When tradeoffs are performed, the source selection records must include the following:
- (A) An assessment of each proposer’s ability to accomplish the technical requirements; and
- (B) A summary, matrix, or quantitative ranking, along with appropriate supporting narrative, of each technical proposal using the evaluation factors.
AUTHORITY: sections 226.020, 226.030, and 227.107, RSMo 2016.* Original rule filed Aug. 15, 2005, effective Feb. 28, 2006. Amended: Filed Dec. 5, 2017, effective July 30, 2018.
*Original authority: 226.020, RSMo 1939; 226.030, RSMo 1939, amended 1965, 2003, 2004, 2009; and 227.107, RSMo 2002, 2007, 2009, 2011, 2016.