PURPOSE: This rule describes the procedure for filing Periodic Progress Reports after approval of Certificate of Need (CON) applications, CONs subject to forfeiture, and the procedure for requesting a cost overrun.
PUBLISHER’S NOTE: The secretary of state has determined that the publication of the entire text of the material which is incorporated by reference as a portion of this rule would be unduly cumbersome or expensive. This material as incorporated by reference in this rule shall be maintained by the agency at its headquarters and shall be made available to the public for inspection and copying at no more than the actual cost of reproduction. This note applies only to the reference material. The entire text of the rule is printed here.
ity CON letter shall file reports by mail or email with the Missouri Health Facilities Review Committee (committee), using Periodic Progress Report (Form MO 580-1871). A report shall be filed within ten (10) days following the end of each six (6)-month period after CON approval, or issuance of a Non- Applicability CON letter, until the project is complete which includes the licensing of all new beds, installation of equipment and/or completion of renovations. All Periodic Progress Reports must contain a complete and accurate accounting of all expenditures for the report period. Final project costs with third-party verification must be provided on a Periodic Progress Report (Form MO 580- 1871).
(4) A CON shall be subject to forfeiture for failure to—
(5) If the CONP staff finds that a CON may be subject to forfeiture—
prior to a committee meeting, the CONP shall notify the applicant in writing of the possible forfeiture, the reasons for it, and its placement on the committee agenda for action; and
(7) Cost overrun review procedures implement the CON statute section 197.315.7, RSMo. Immediately upon discovery that a project’s actual costs would exceed approved project costs by more than ten percent (10%), the applicant shall apply for approval of the cost variance. A nonrefundable fee in the amount of one-tenth of one percent (0.1%) of the additional project cost above the approved amount made payable to “Missouri Health Facilities Review Committee” shall be required. The information requirements for a cost overrun review are required as follows:
(A) Amount and justification for cost overrun shall document—
costs would be exceeded, including a detailed listing of the areas involved;
scope of the project as originally approved; and
run that were considered and why this particular approach was selected; and
(9) The following forms cited in this rule are incorporated by reference and published by the Certificate of Need Program (CONP), December 13, 2019, and may be downloaded from http://health.mo.gov/information/boards/certificateofneed/forms.php, obtained by emailing a written request to CONP@health.mo.gov, or acquire in person at the CONP Office, 3418 Knipp Drive, Suite F, Jefferson City, Missouri, 65102 (573) 751-6403. This rule does not include any later amendments or additions.
AUTHORITY: section 197.320, RSMo 2016.* Original rule filed June 2, 1994, effective Nov. 30, 1994. Emergency rescission and rule filed Aug. 29, 1997, effective Sept. 8, 1997, expired March 6, 1998. Rescinded and readopted: Filed Aug. 29, 1997, effective March 30, 1998. Amended: Filed Oct. 19, 1999, effective April 30, 2000. Emergency rescission and rule filed Dec. 14, 2001, effective Jan. 1, 2002, expired June 29, 2002. Rescinded and readopted: Filed Dec. 14, 2001, effective June 30, 2002. Emergency rescission and rule filed Dec. 16, 2002, effective Jan. 1, 2003, expired June 29, 2003. Amended: Filed June 9, 2003, effective Nov. 30, 2003. Emergency amendment filed Aug. 14, 2006, effective Aug. 28, 2006, expired Feb. 23, 2007. Amended: Filed Aug. 14, 2006, effective March 30, 2007. Amended: Filed Oct. 1, 2010, effective May 30, 2011. Amended: Filed Aug. 9, 2019, effective March 30, 2020.