Mo. Code Regs. Ann. tit. 13, § 70-10.100
PURPOSE: This rule establishes a limitation on the allowance of capital cost overruns in the construction of new institutional health services for Title XIX reimbursement rate setting purposes.
(1) For implementation purposes of this rule, the following definitions shall apply:
(B) Initial project estimate—
Missouri Health Facilities Review Committee issued a Certificate of Need (CON); or
received a CON, is the dollar amount specified on the binding construction or purchase contract which was executed prior to October 1, 1980;
services in excess of ten percent (10%) of the initial project estimates shall not be considered in establishing a Title XIX per-diem rate for the first thirty-six (36) months that a facility receives payment for services provided under section 208.152, RSMo for any facility that applies for approval or consent for a cost overrun on or after November 11, 1982. This limitation is effective whether or not approval is granted under section 197.315.7, RSMo. If approval or consent is given, a facility’s cost overrun will be considered in establishing a Title XIX per-diem rate after the thirty-six (36)-month period in accordance with the provisions of the Title XIX reimbursement plan applicable to the provider type and subject to the limitations.
AUTHORITY: sections 207.020, RSMo Supp. 1993, 208.159, RSMo 1986 and 208.153, RSMo Supp. 1991.* This rule was previously filed as 13 CSR 40-81.082. Emergency rule filed Aug. 5, 1982, effective Aug. 15, 1982, expired Nov. 10, 1982. Original rule filed Aug. 5, 1982, effective Nov. 11, 1982. *Original authority: 207.020, RSMo 1945, amended 1961, 1965, 1977, 1981, 1982, 1986, 1993; 208.153, RSMo 1967, amended 1967, 1973, 1989, 1990, 1991; and 208.159, RSMo 1979.