PURPOSE: This rule contains the requirements for scrap tire processing facility permits.
PUBLISHER’S NOTE: The secretary of state has determined that the publication of the entire text of the material which is incorporated by reference as a portion of this rule would be unduly cumbersome or expensive. This material as incorporated by reference in this rule shall be maintained by the agency at its headquarters and shall be made available to the public for inspection and copying at no more than the actual cost of reproduction. This note applies only to the reference material. The entire text of the rule is printed here.
(1) Definitions. Definitions for key words used in this rule may be found in section 260.200, RSMo. Additional definitions specific to this rule are as follows:
(A) A scrap tire is a tire that is no longer suitable for its original intended purpose because of wear, damage or defect.
nal intended purpose due to wear is a tire with exposed cord or tread depth less than two thirty-seconds of an inch (2/32") when measured in any major groove.
intent of final disposal is also a scrap tire.
al in a permitted solid waste disposal area, is a scrap tire cut in half circumferentially; sidewalls removed from tread; or cut into at least three (3) parts with no part being larger than approximately one-third (1/3) of the original tire’s size.
purposes of disposal in a permitted solid waste disposal area, is a scrap tire that has been reduced to parts no larger than that defined in the definition of a cut tire.
(2) General Requirements.
(3) Applicability.
(A) Permit Exemptions. The following persons are not required to obtain a scrap tire processing permit provided that pollution, a public nuisance or a health hazard is not created and provided the tires are stored according to the requirements of section (5) of this rule:
twenty-five (25) tires at the facility at all times;
sively processes scrap tires generated solely at the collection center, provided that the processing is done using the collection center’s employees and processing equipment and provided the processing takes place at the collection center where the scrap tires are generated; and
with a permitted scrap tire processing facility for the processing and proper disposal of scrap tires generated solely at the collection center.
(4) Scrap Tire Processing Facility Permit Application.
(B) An application for a scrap tire processing facility permit shall be sent by certified mail to the Missouri Department of Natural Resources, Solid Waste Management Program, PO Box 176, Jefferson City, MO 65102-0176. The application shall consist of:
Facility Permit Application form which will be provided by the department;
plans containing the information necessary to comply with the storage and record keeping requirements of this rule. Plans shall include:
scrap tires that can be processed or used in six (6) months of normal and continuous operation. This estimate shall be based on the volume of tires processed or used by the facility in the last year, or the manufacturer’s estimated capacity of the processing equipment. This estimate may be increased when new equipment is obtained by the owner of the facility and may be reduced if equipment used previously is removed from active use. Active use will be determined on a case-bycase basis and will be based on the provisions of the permit;
prepared by a registered land surveyor showing contour intervals of ten feet (10') or less. This survey shall have a scale of not less than one inch equals four hundred feet (1"=400'). All existing and proposed storage areas and structures shall be shown on the survey;
zoning within five hundred feet (500') of the property boundaries, including the location of all residences, buildings, utilities and easements. This map shall have a scale of not less than one inch equals four hundred feet (1"= 400'); and
information necessary to comply with the closure requirements and financial assurance instrument requirements of this rule;
mize the hazards to human health and the environment from fires, runoff of contaminants resulting from fires and from mosquitoes in case of failure of the primary method of vector control. The contingency plan shall include, but not be limited to, the following items, as applicable:
take in response to fires, runoff resulting from fires and mosquito breeding in scrap tires;
nel, in case of fire; and
plan has been provided to the local fire and police departments;
tires;
department’s Clean Water Law, Chapter 644, RSMo and implementing regulations;
zoning requirements;
the property owner, if different from the applicant, for land use for scrap tire storing and processing operations; and
mit fee of two hundred dollars ($200). The fee shall be paid by certified check or money order made payable to the Missouri Department of Natural Resources.
(D) Application Review, Approval and Denial. The department will complete an investigation of the application to determine compliance with the requirements of sections 260.200–260.345, RSMo, and corresponding rules, and render a decision to the applicant. When the investigation reveals that the scrap tire processing facility application either:
tions 260.200–260.345, RSMo, and corresponding rules, the department will approve the application and issue a permit; or
of sections 260.200–260.345, RSMo, and corresponding rules, the department will issue a written denial to the applicant, including the reasons for denial.
(E) Permit Issuance, Suspension, Revocation and Modification.
facility will be issued to the owner/operator for the life of the facility.
may be revoked or suspended for noncompliance with the provisions of sections 260.200– 260.345, RSMo or corresponding rules.
ing the life of the permit, open and modify or alternately revoke the permit and require the permittee to comply with any currently applicable federal, state or local requirements.
(5) Storage Requirements.
(A) Fire Protection.
processing facility shall provide written evidence from the local fire protection agency that indoor and outdoor storage of whole or processed scrap tires complies with the currently applicable local or state fire protection standards, or the scrap tire processing facility must comply with the 2006 International Fire Code, published by the International Code Council, Inc., 4051 W. Flossmoor Road, Country Club Hills, IL, 60478-5795, copyright 2006, which by this reference is incorporated into this rule. This rule does not incorporate any subsequent amendments or additions.
least the one hundred (100)-year design flood by impervious dikes or other appropriate means to prevent the flood waters from contacting the scrap tires).
(E) Vector Control. Conditions shall be maintained that are unfavorable for the harboring, feeding and breeding of vectors. If the method being used to control vectors is not effective, the owner/operator of the scrap tire processing facility shall use an alternative method to correct the vector problem. The owner/operator of a scrap tire processing facility shall use one (1) or more of the following methods of vector control:
within a building, enclosed trailer or under a cover that is water impermeable. The cover shall be maintained to be water impermeable;
adulticide appropriate to prevent the development of mosquito larvae and pupae and repeat treatment as often as necessary to prevent such development, taking into account the effectiveness and life of the larvicide and/or adulticide utilized.
be applied in accordance with their label, Chapter 281, RSMo and its implementing regulations.
the method of stacking the tires shall allow for application of the larvicide and/or adulticide to all tires.
must be approved by the department if documented to control larvae, pupae and adult mosquitoes.
(6) Record Keeping Requirements. The owner/operator of a scrap tire processing facility shall maintain the records required by this rule. All records required by this rule shall be kept for at least three (3) years. The period of record retention extends upon the written request of the department or automatically during the course of any unresolved enforcement action regarding the regulated activity. The records shall be made available for inspection by the department or its designated representative upon request. The records shall include at least the following:
(C) Records of Vector Control Activities. For a scrap tire processing facility utilizing a larvicide and/or adulticide for vector control, the records shall include the following:
by a registered pest control company, the name of the company and the date of application; or
applied by a registered pest control company, type(s) of larvicide/adulticide utilized, amount utilized and date applied.
(7) Closure, Financial Assurance.
(A) Exemptions. The following are not required to establish a closure plan and financial assurance instrument provided that pollution, a public nuisance or a health hazard is not created and provided the scrap tires are stored according to the requirements of section (5) of this rule:
ted by the department;
ted by the department, at which less than five hundred (500) scrap PTE are stored at any time.
(B) Closure Plan Requirements.
cessing facility shall include methods, time schedules and cost estimates for removal of all scrap tires and site clean-up and restoration activities. The cost estimates for the amount of the financial assurance instrument shall be based upon the current costs of similar cleanups using data from actual scrap tire cleanup project bids received by the department to remediate scrap tire sites of similar size. The following shall be performed as a part of closure of a scrap tire processing facility and shall be included in the plans:
cost estimates. Scrap tires shall be removed from the site and taken to a Missouri facility that has obtained applicable permits from the department or taken out-of-state (provided that transport and final destinations are in compliance with the requirements of that state). The site shall be cleaned up so as to remove all other solid waste to provide a pleasing appearance;
mates. If necessary, removal of any contaminated soil, debris, residue, and/or placement of cover and establishment of vegetation in a manner as to minimize erosion, control drainage and provide a pleasing appearance. For the purposes of financial assurance instruments, the cost of removal of at least fifty percent (50%) of processed scrap tire material that has been reduced to parts no larger than one-half inch (1/2") nominal;
strate in the closure plan that the estimate represents the maximum closure costs at any time during the active operation of the scrap tire site;
with the closure plan shall contain an estimate in current dollars (based upon the current costs of similar cleanups using data from actual scrap tire clean-up project bids received by the department to remediate scrap tire sites of similar size) and an adjusted estimate for the succeeding five (5) years based on the projected rate of inflation. The rate of inflation used for this purpose shall be the latest percent change in the Implicit Price Deflator for the Gross Domestic Product for the latest completed year, as determined by the United States Department of Commerce, Bureau of Economic Analysis. The adjusted cost estimate shall be used to determine the amount of the financial assurance instrument; and
adjusted every five (5) years by the owner/operator based upon the actual rate of inflation for the preceding five (5) years and the projected rate of inflation for the succeeding five (5) years. The adjusted cost estimates shall be submitted to the department for review every five (5) years after the date of permit issuance.
processing facility shall notify the department in writing at least ninety (90) days prior to the date the owner/operator expects to begin closure. The owner/operator shall begin implementation of the closure plan required in this rule within thirty (30) days after the closure date specified in the closure plan.
tire processing facility as a part of closure of the scrap tire site, shall execute an easement with the department, which allows the department, its agents or its contractors to enter the premises to complete work specified in the closure plan, to monitor or maintain the scrap tire site, or take remedial action. This easement will be terminated upon proper closure of the site.
ation of a scrap tire processing facility make modifications in the closure plans or cost estimates necessary, modified closure plans and cost estimates shall be submitted to the department for approval prior to implementation of the changes.
(C) Financial Assurance Requirements.
financial assurance instruments as required by subsection (7)(C) of this rule have been submitted and approved by the department.
cial assurance instruments. The following shall apply to all financial assurance instruments as specified in paragraph (7)(C)2. of this rule except the financial test, corporate guarantee and insurance: When the estimated closure cost increases, the amount of the financial assurance instrument shall be adjusted to cover the increase in the cost estimate. The owner/operator shall increase the amount of the financial assurance instrument within one hundred eighty (180) days of the increase in the estimate and submit written evidence of the increase to the director or obtain other financial assurance as specified in paragraph (7)(C)2. of this rule to cover the increase. If the current closure cost decreases and the owner/operator has received written approval from the director of this decrease, the owner/operator may decrease the amount of the closure financial assurance instrument.
ance instruments. The department will inspect a permitted scrap tire processing facility when notified by the owner/operator that the closure plan has been implemented. If the inspection reveals that the approved closure plan has been properly effected, the director shall authorize the release or proportional release of the financial assurance instrument submitted for closure and interest, if any.
instruments. If the owner/operator fails to properly implement the closure plan, the director will give written notice of the violation and order the owner/operator to implement the closure plan. If corrective measures approved by the director are not commenced within a specified and reasonable time, the director will order forfeiture of all or that part of the owner/operator’s financial assurance instrument necessary to implement the closure plans. Any owner/operator aggrieved by a forfeiture order may appeal as provided in section 536.150, RSMo.
requirements of subsection (7)(C) of this rule for financial assurance instrument(s) for closure may be satisfied by establishing a trust fund or escrow account, securing a financial guarantee bond or a performance bond, obtaining an irrevocable letter of credit, insurance, or a combination of these as outlined in paragraph (7)(C)2. of this rule. This requirement may also be satisfied by meeting a financial test and by using a corporate guarantee. A municipality or county may satisfy the requirements by signing a contract of obligation.
establishment of a trust fund or escrow account may be used to satisfy the requirement for a financial assurance instrument to provide for closure.
tution which is authorized to administer trusts in Missouri and whose trust operations are regulated and examined by Missouri or a federal agency shall act as the trustee of the closure trust fund. An escrow account shall be established at a bank or financial institution which is located in Missouri and which is examined by Missouri or a federal agency.
account shall consist of cash, certificates of deposit or United States government securities. United States government securities include treasury bills, treasury bonds and treasury notes guaranteed by the federal government.
escrow account agreements.
agreement must be identical to the wording specified in form MO 780-1272 and the trust fund agreement must be accompanied by a formal certification of acknowledgment form MO 780-1271. An original or an originally signed duplicate of the trust fund agreement shall be submitted to the department.
account agreement shall be identical to the wording in form MO 780-1264. An original or an originally signed duplicate of the escrow account agreement shall be submitted to the department.
lishes a trust fund or escrow account after having used one (1) or more alternate mechanisms specified in paragraph (7)(C)2. of this rule, the first payment must be in at least the amount that the trust fund or escrow account would contain if the trust fund or escrow account were established initially and annual payments made based upon the current costs of similar cleanups using data from actual scrap tire clean-up project bids received by the department to remediate scrap tire sites of similar size.
tutes other financial assurance as specified in subsection (7)(C) of this rule for all or part of the trust fund or escrow account, s/he may submit a written request to the department for release of all or a portion of the amount covered by the trust fund or escrow account.
receiving a request from the owner/operator for release of funds as specified in part (7)(C)2.A.(V) of this rule, the director will instruct the trustee or escrow agent to release to the owner/operator those funds as the director specifies in writing.
not properly implement the closure plan and does not comply with an order by the department to do so, the department will order the forfeiture of all or part of the trust fund or escrow account as specified in subparagraph (7)(C)1.C. of this rule. (VIII) The director will agree to termination of the trust fund or escrow account when:
tutes alternate financial assurance as specified in subsection (7)(C) of this rule; or
owner/operator from the requirements of subsection (7)(C) of this rule.
requirement for a financial assurance instrument may be satisfied by securing a financial guarantee bond.
the owner/operator and a corporate surety licensed to do business in Missouri. The surety company issuing the bond, at a minimum, must be among those listed as acceptable sureties on federal bonds in Circular 570 of the United States Department of the Treasury. Corporate surety companies that issue sureties in which the penal sums (face amounts) exceed the corporation’s underwriting limitation must provide proof of coinsurance, reinsurance, or provide another method of assurance in accordance with Treasury Circular 297, Revised September 1, 1978, (31 CFR sections 223.10-11).
must be identical to the wording specified in form MO 780-1265.
a surety bond to satisfy the requirements of subsection (7)(C) of this rule must also establish a standby trust fund or escrow account. Under the terms of the bond, all payments made will be deposited by the surety directly 10 CSR 80-8
into the standby trust fund or escrow account in accordance with instructions from the director. This standby trust fund or escrow account must meet the requirements specified in subparagraph (7)(C)2.A. of this rule except that:
signed duplicate of the standby trust fund or escrow account agreement must be submitted to the department with the surety bond; and
or escrow account is funded pursuant to the requirements of subparagraph (7)(C)2.B. of this rule, the following are not required by these rules:
fund or escrow account;
required by the trust fund or escrow account agreement; and
as required by the trust fund or escrow account agreement.
the owner/operator will:
or escrow account in an amount equal to the penal sum of the bond before the beginning of final closure of the scrap tire site;
or escrow account in an amount equal to the penal sum within thirty (30) days after an order to begin closure is issued by the department; or
assurance as specified in subsection (7)(C) of this rule; and within ninety (90) days after receipt, by both the owner/operator and the department, of a cancellation notice of the bond from the surety, obtain the director’s written approval of the provided assurance.
the surety will become liable on the bond obligation when the owner/operator fails to perform as guaranteed by the bond.
the surety may cancel the bond by sending notice of cancellation by certified mail to the owner/operator and to the department. Cancellation may not occur, however, during the one hundred twenty (120) days beginning on the date of receipt of the notice of cancellation by both the owner/operator and the director, as evidenced by the return receipts.
cel the bond if the director has given prior written consent based on receipt of evidence of alternate financial assurance as specified in subsection (7)(C) of this rule.
ment for a financial assurance instrument may be satisfied by securing a performance bond guaranteeing performance of closure.
the owner/operator and a corporate surety licensed to do business in Missouri. The surety company issuing the bond, at a minimum, must be among those listed as acceptable sureties on federal bonds in Circular 570 of the United States Department of the Treasury. Corporate surety companies that issue sureties in which the penal sums (face amounts) exceed the corporation’s underwriting limitation must provide proof of coinsurance, reinsurance, or provide another method of assurance in accordance with Treasury Circular 297, Revised September 1, 1978, (31 CFR sections 223.10-11).
must be identical to the wording specified in form MO 780-1266.
a surety bond to satisfy the requirements of subsection (7)(C) of this rule must also establish a standby trust fund or escrow account. Under the terms of the bond, all payments made will be deposited by the surety directly into the standby trust fund or escrow account in accordance with instructions from the director. This standby trust fund or escrow account must meet the requirements specified in subparagraph (7)(C)2.A. of this rule, except that:
signed duplicate of the standby trust fund or escrow account agreement must be submitted to the department with the surety bond; and
or escrow account is funded pursuant to the requirements of subparagraph (7)(C)2.C. of this rule, the following are not required by these rules:
or escrow account as specified;
required by the trust fund or escrow account agreement; and
required by the trust fund or escrow account agreement.
the owner/operator will:
accordance with the closure plan and other requirements of the scrap tire processing facility permit whenever required to do so; or
assurance as specified in subsection (7)(C) of this rule and obtain the director’s written approval of the provided assurance, within ninety (90) days after receipt by both the owner/operator and the department of a notice of cancellation of the bond from the surety.
the surety will become liable on the bond obligation when the owner/operator fails to perform as guaranteed by the bond. Following a determination that the owner/operator has failed to perform final closure in accordance with the closure plan, under the terms of the bond the surety will perform final closure as guaranteed by the bond or will deposit the amount of the penal sum into the standby trust fund or escrow account.
the surety may cancel the bond by sending notice of cancellation by certified mail to the owner/operator and to the department. Cancellation may not occur, however, during the one hundred twenty (120) days beginning on the date of receipt of the notice of cancellation by both the owner/operator and the department, as evidenced by the return receipts.
cel the bond if the director has given prior written consent. The director will provide written consent when:
tutes alternate financial assurance as specified in subsection (7)(C) of this rule; or
owner/operator from the requirements of subsection (7)(C) of this rule. (VIII) The surety will not be liable for deficiencies in the performance of closure by the owner/operator after the director releases the owner/operator from the requirements of subsection (7)(C) of this rule.
for a financial assurance instrument may be satisfied by obtaining an irrevocable standby letter of credit.
issued by a stateor federally-chartered and regulated bank or trust association. If the issuing institution is not located in Missouri, a bank or trust association located in Missouri must confirm the letter of credit and the confirmation shall be filed with the department along with the letter of credit.
credit must be identical to the wording specified in form MO 780-1267.
letter of credit to satisfy the requirements of subsection (7)(C) of this rule must also establish a standby trust fund or escrow account. Under the terms of the letter of credit, all amounts paid pursuant to a draft by the director will be deposited by the issuing institution directly into the standby trust fund or escrow account in accordance with instructions from the director. This standby trust fund or escrow account must meet the requirements of the trust fund or escrow account specified in subparagraph (7)(C)2.A. of this rule, except that:
signed duplicate of the standby trust fund or escrow account agreement must be submitted to the department with the letter of credit; and
or escrow account is funded pursuant to the requirements of subparagraph (7)(C)2.D. of this rule, the following are not required by these rules:
or escrow account as specified;
required by the trust fund or escrow account agreement; and
required by the trust fund or escrow account agreement.
accompanied by a letter from the owner/operator referring to the letter of credit by number, the issuing institution and date and providing the following information: the scrap tire processing facility permit number, name and address of the scrap tire processing facility and the amount of funds assured for closure of the scrap tire processing facility by the letter of credit.
irrevocable and issued for a period of at least one (1) year. The letter of credit must provide that the expiration date will be automatically extended for a period of at least one (1) year unless, at least one hundred twenty (120) days before the current expiration date, the issuing institution notifies both the owner/operator and the department by certified mail of a decision not to extend the expiration date. Under the terms of the letter of credit, the one hundred twenty (120) days will begin on the date when both the owner/operator and the department have received the notice, as evidenced by the return receipts.
establish alternate financial assurance as specified in subsection (7)(C) of this rule and obtain written approval of this alternate assurance from the director within ninety (90) days after receipt by both the owner/operator and the department of a notice from the issuing institution that it has decided not to extend the letter of credit beyond the current expiration date, the director will draw on the letter of credit. The director may delay the drawing if the issuing institution grants an extension of the term of the credit. During the last thirty (30) days of this extension, the director will draw on the letter of credit if the owner/operator has failed to provide alternate financial assurance as specified in subsection (7)(C) of this rule and obtain written approval of that assurance from the director.
that the owner/operator has failed to perform final closure in accordance with the closure plan and other permit requirements when required to do so, the director may draw on the letter of credit. (VIII) The director will return the letter of credit to the issuing institution for termination when:
tutes alternate financial assurance as specified in subsection (7)(C) of this rule; or
owner/operator from the requirements of subsection (7)(C) of this rule.
financial assurance instrument may be satisfied by obtaining insurance. The insurance policy shall be irrevocable and without provisions to transfer, loan/borrow, withdraw, make premium payments from or otherwise extract or encumber funds from the face amount or cash surrender value of the policy, except upon written approval by the director or his/her designee.
shall be licensed to transact the business of insurance, or be eligible to provide insurance as an admitted or an excess or surplus lines insurer, in one (1) or more states, and authorized to transact business in Missouri by law and by the Missouri Department of Insurance, Financial Institutions and Professional Registration.
of insurance must be identical to the wording specified in form MO 780-1268.
issued for a face amount at least equal to the amount specified in paragraph (7)(B)1. of this rule. The term face amount means the total amount the insurer is obligated to pay under the policy. Actual payments by the insurer will not change the face amount, although the insurer’s future liability will be lowered by the amount of the payments.
guarantee that funds will be available to close the scrap tire processing facility whenever final closure occurs. The policy must also guarantee that once the final closure begins, the insurer, upon the direction of the director, will be responsible for paying out funds, up to an amount equal to the face amount of the policy, to that party(ies) as the director specifies. Release of the funds will be authorized by the director according to paragraph (7)(C)1. of this rule.
maintain the policy in full force and effect until the director consents to termination of the policy by the owner/operator as specified in part (7)(C)2.E.(VIII) of this rule. Failure to pay the premium, without substitution of alternate financial assurance as specified in subsection (7)(C) of this rule, will constitute a significant violation of these rules, warranting such remedy as the director deems necessary. The violation will be deemed to begin upon receipt by the department of a notice of future cancellation, termination, or failure to renew due to nonpayment of the premium, rather than upon the date of expiration.
visions:
policy to a successor owner/operator. The assignment may be conditional upon consent of the insurer, provided the consent is not unreasonably refused;
on a claims-made basis shall provide retroactive coverage from the date of issuance of said policy covering the facility and shall contain an extended claims reporting period of at least twelve (12) months; and
Missouri Department of Natural Resources as the irrevocable primary beneficiary without collateral assignment(s).
the insurer may not cancel, terminate or fail to renew the policy except for failure to pay the premium. The automatic renewal of the policy, at a minimum, must provide the insured with the option of renewal at the face amount of the expiring policy. If there is a failure to pay the premium, the insurer may elect to cancel, terminate or fail to renew the policy by sending notice by certified mail to the owner/operator and the department. Cancellation, termination or failure to renew may not occur, however, during the one hundred twenty (120) days beginning with the date of receipt of the notice by both the director and the owner/operator, as evidenced by the return receipts. Cancellation, termination or failure to renew may not occur and the policy will remain in full force and effect in the event that on or before the date of expiration:
site abandoned;
revoked or a new permit is denied;
director or a United States district court or other court of competent jurisdiction; 10 CSR 80-8
as debtor in a voluntary or involuntary proceeding under Title 11 (Bankruptcy), United States Code; or
ten consent to the owner/operator that s/he may terminate the insurance policy when:
tutes alternate financial assurance as specified in subsection (7)(C) of this rule; or
owner/operator from the requirements of subsection (7)(C) of this rule.
antee. The requirements for a financial assurance instrument may be satisfied by passing a financial test. A corporate guarantee submitted by the parent corporation of the owner/operator as specified in part (7)(C)2.F.(X) of this rule may also be used to satisfy the requirements for a financial assurance instrument.
owner/operator must meet the criteria of either subpart (7)(C)2.F.(I)(a) or (b) of this rule.
have:
three (3) ratios: a ratio of total liabilities to net worth less than 2.0; a ratio of the sum of net income plus depreciation, depletion and amortization to total liabilities greater than 0.1; and a ratio of current assets to current liabilities greater than 1.5;
2.0 times the sum of the current closure cost estimates covered by the test; and
amounting to at least ninety percent (90%) of his/her total assets or at least 2.0 times the sum of the current closure cost estimates covered by the test.
have:
most recent bond issuance of AAA, AA, A or BBB as issued by Standard and Poor’s or Aaa, Aa, A or Baa as issued by Moody’s;
2.0 times the sum of the current closure cost estimates covered by the test; and
ed States amounting to at least ninety percent (90%) of his/her total assets or at least 2.0 times the sum of the current closure cost estimates covered by the test.
estimates as used in part (7)(C)2.F.(I) of this rule refers to the cost estimates required to be shown in paragraphs 1.–4. of the letter from the owner/operator’s chief financial officer form MO 780-1269.
this test, the owner/operator must submit the following items to the department:
owner/operator’s chief financial officer and worded as specified in form MO 780-1269;
certified public accountant’s report on examination of the owner/operator’s financial statements for the latest completed fiscal year based on generally accepted accounting principles; and
owner/operator’s independent certified public accountant to the owner/operator stating that:
which the letter from the chief financial officer specifies as having been derived from the independently audited, year-end financial statements for the latest fiscal year with the amounts in those financial statements; and
that the certified public accountant provide assurance must be consistent with current professional auditing standards.
items specified in part (7)(C)2.F.(III) of this rule, the owner/operator must send updated information to the department within ninety (90) days after the close of each succeeding fiscal year. This information must consist of all three (3) items specified in part (7)(C)2.F.(III) of this rule.
meets the requirements of part (7)(C)2.F.(I) of this rule, s/he must send notice to the department of intent to establish alternate financial assurance. The notice must be sent by certified mail within ninety (90) days after the end of the fiscal year for which the yearend financial data show that the owner/operator no longer meets the requirements. The owner/operator must provide the alternate financial assurance within one hundred twenty (120) days after the end of the fiscal year.
sonable belief that the owner/operator may no longer meet the requirements of part (7)(C)2.F.(I) of this rule, may require reports of financial condition at any time from the owner/operator in addition to those specified in part (7)(C)2.F.(I) of this rule. If the director finds, on the basis of the reports or other information, that the owner/operator no longer meets the requirements of part (7)(C)2.F.(I) of this rule, the owner/operator must provide alternative financial assurance as specified in subsection (7)(C) of this rule within thirty (30) days after notification of such a finding.
and evaluate additional information which relates to financial status, including present or potential environmental liabilities and may deny the use of the financial test based upon the evaluation or the failure of an applicant to provide such additional information requested by the department within thirty (30) days from the date of that request. Pending approval of the use of the test by the director or pending appeal before any court of competent jurisdiction of the department’s denial of the use of the test, the owner/operator shall comply with the financial assurance requirements through the use of an alternate financial assurance mechanism as described in subsection (7)(C) of this rule. The burden of proof shall be on the applicant in the event of any appeal of a denial. If the department rules that the firm’s financial test is unacceptable, the firm shall have thirty (30) days from the date of notification of such a decision to provide alternative financial assurances. (VIII) The department may disallow use of this test on the basis of qualifications in the opinion expressed by the independent certified public accountant in the report on examination of the owner/operator’s financial statements. An adverse opinion or a disclaimer of opinion will be cause for disallowance. The department will evaluate other qualifications on an individual basis. The owner/operator must provide alternate financial assurance as specified in subsection (7)(C) of this rule within thirty (30) days after notification of the disallowance.
longer required to submit the items specified in part (7)(C)2.F.(III) of this rule when:
tutes alternate financial assurance as specified in subsection (7)(C) of this rule; or
owner/operator from the requirements of subsection (7)(C) of this rule.
the requirements of subsection (7)(C) of this rule by obtaining a written guarantee, referred to in this rule as corporate guarantee. The guarantor must be the parent corporation of the owner/operator. The guarantor must meet the requirements for owner/operators in parts (7)(C)2.F.(I)–(VIII) of this rule and must comply with the terms of the corporate guarantee. The wording of the corporate guarantee must be identical to the wording specified in form MO 780-1270. The corporate guarantee must accompany the items sent to the department as specified in part (7)(C)2.F.(III) of this rule. The terms of the corporate guarantee must provide that:
perform final closure of a scrap tire processing facility covered by the corporate guarantee in accordance with the closure plan and other permit requirements whenever required to do so, the guarantor will do so or establish a trust fund as specified in subparagraph (7)(C)2.A. of this rule in the name of the owner/operator;
remain in force unless the guarantor sends notice of cancellation by certified mail to the owner/operator and to the department. Cancellation may not occur, however, during the one hundred twenty (120) days beginning on the date of receipt of the notice of cancellation by both the owner/operator and the department, as evidenced by the return receipts; and
provide alternate financial assurance as specified in subsection (7)(C) of this rule and obtain the written approval of the alternate assurance from the director within ninety (90) days after receipt by both the owner/operator and the department of a notice of cancellation of the corporate guarantee from the guarantor, the guarantor will provide the alternative financial assurance in the name of the owner/operator.
ities or counties may satisfy the requirements for a financial assurance instrument by entering into a contract of obligation for the full amount of the approved closure cost estimates. The wording of the contract of obligation shall be identical to the wording specified in form MO 780-1263.
be a binding agreement on the municipality or county, allowing the department to collect the required amount from any funds being disbursed or to be disbursed by Missouri to the municipality or county. A municipality or county that uses the contract of obligation every five (5) years shall submit a letter to the department from the governing body reaffirming the amount of their financial obligation. The wording of the contract of obligation shall be identical to the wording specified in the Contract of Obligation form.
The Contract of Obligation shall be submitted to the department by the owner/operator with an attached Resolution or Ordinance specifying the name of the Signatory Agent having the designated authority to sign the Contract of Obligation. The Resolution or Ordinance shall contain wording similar to the wording specified in the Resolution/Ordinance form.
Test. The Contract of Obligation shall be submitted to the department every five (5) years by the owner/operator with an attached, accurate and complete Local Government Financial Test. The Local Government Financial Test shall contain:
owner/operator’s chief financial officer using wording identical to the wording specified in the Local Government Financial Test form;
certified public accountant’s report on examination of the owner/operator’s financial statements for the latest completed fiscal year; and
independent certified public accountant to the owner/operator stating that—
which the letter from the chief financial officer specifies as having been derived from the independently audited, year-end financial statements for the latest fiscal year with the amounts in the financial statements;
appropriate description of the findings using a summary of findings in accordance with the requirements of the American Institute of Certified Public Accountants Statement on Auditing Standards #75; and
dure was performed in accordance with generally accepted accounting principles (GAAP).
include a copy of the most recent comprehensive annual financial report (CAFR) disclosing, for public notice, all of the estimated scrap tire processing facility closure financial obligations. The report shall include:
closure requirements;
incurred.
terms used in this rule shall be consistent with generally accepted accounting principles (GAAP).
(VI) Qualifications.
be qualified to utilize Contracts of Obligation and Local Government Financial Tests if they have been determined to:
waste management district or organization other than a county or incorporated city, town or village, as classified in Article VI, Section 15, of the Constitution of Missouri. Two (2) or more qualified local governments may join in common to submit combined mechanisms;
any outstanding general obligation bonds;
eral obligation bonds having a Standard and Poor’s rating less than BBB or a Moody’s rating less than Baa;
exceeding five percent (5%) of the total annual revenues in each of the past two (2) years, except as allowed in Article VI, Sections 26(a) through 26(g), of the Constitution of Missouri;
old in excess of forty-three percent (43%) of the local government’s total annual revenues. This rule allows the annual guaranteed environmental financial assurances to sub-total up to forty-three percent (43%) of the total annual revenues with additional secured financial assurance mechanism(s) being demonstrated for the remaining balance;
or a disclaimer of opinion from an independent certified public accountant as reported under subparagraphs (7)(C)2.G.(III)(b) and (7)(C)2.G.(III)(c) of this rule; and
of subparagraph (7)(C)2.G.(VI)(b)I. of this rule.
under subparagraph (7)(C)2.G.(VI) of this rule shall pass the local government financial test by meeting the criteria of either parts (7)(C)2.G.(VI)(b)I., Alternative I, or (7)(C)2.G.(VI)(b)II., Alternative II, of this rule as follows:
owner/operator shall have a liquidity ratio greater than or equal to 0.050 and a debt service ratio less than or equal to 0.20; or
owner/operator shall have a current rating for all outstanding general obligation bonds of AAA, AA, A or BBB as issued by Standard and Poor’s or Aaa, Aa, A or Baa as issued by Moody’s. Ratings from agencies other than Standard and Poor’s or Moody’s and ratings on expired bonds, refunding bonds, revenue bonds, insured bonds or structured financing (guaranteed or collateralized) are not acceptable.
(VII) Effective dates.
ers/operators of active scrap tire processing facilities, choosing to use a Contract of Obligation to guarantee scrap tire processing facility financial assurance, shall submit a Local Government Financial Test and a Comprehensive Annual Financial Report, using the most recent fiscal financial statements, with each Contract of Obligation and Resolution/Ordinance submitted on or after April 9, 10 CSR 80-8
1998. After initial approval, each owner/operator shall every five (5) years submit an updated Contract of Obligation and Resolution/Ordinance, Local Government Financial Test and Comprehensive Annual Financial Report within one hundred eighty (180) days following the end of their fiscal year.
cially closed facilities, having properly executed Contracts of Obligation that were approved prior to April 9, 1998, are not required to submit a Local Government Financial Test nor a Comprehensive Annual Financial Report as long as they are in compliance with 10 CSR 80-2.030 at the time of closure. The cost estimates of the Contracts of Obligation for officially closed facilities may be every five (5) years adjusted for inflation, as specified in subsection (7)(C)1.A. of this rule, by using a cover letter amendment to the contract signed by the designated signatory agent.
ance instruments. An owner/operator may satisfy the requirements of subsection (7)(C) of this rule for financial assurance instruments by establishing more than one (1) financial instrument per scrap tire processing facility for closure. These instruments are limited to trust funds, escrow accounts, financial guarantee bonds, and letters of credit. The instrument must be as specified in paragraph (7)(C)2. of this rule except that it is the combination of instruments, rather than the single instrument which must provide financial assurance for an amount at least equal to an amount based upon the current costs of similar cleanups using data from actual scrap tire clean-up project bids received by the department to remediate scrap tire sites of similar size. If an owner/operator uses a trust fund or escrow account in combination with a surety bond or a letter of credit, s/he may use the trust fund or escrow account as the standby trust fund or escrow account for the other instruments. A single standby trust fund or escrow account may be established for two (2) or more instruments. The director may use any or all of the instruments to provide for closure of the scrap tire site.
financial assurance instruments. When increases in the financial assurance instrument are no longer being made and the estimated closure cost increases, the amount of the financial assurance instrument shall be adjusted to cover the increase in the cost estimate. The owner/operator shall increase the amount of the financial assurance instrument within sixty (60) days of the increase in the estimate and submit written evidence of the increase to the director or obtain other financial assurance as specified in subsection (7)(B) of this rule to cover the increase. If the current cost of closure decreases and the owner/operator has received written approval from the director of a decrease, the owner/operator may decrease the amount of the closure financial assurance instrument.
instruments. The department will inspect a permitted scrap tire processing facility when notified by the owner/operator that the closure plan has been implemented. If the inspection reveals that the approved closure plan has been properly effected, the director shall authorize the release or proportional release of, the financial assurance instrument submitted for closure and interest, if any.
instruments. If the owner/operator fails to properly implement the closure plan, the director will give written notice of the violation and order the owner/operator to implement the closure plan. If closure as approved by the director has not commenced within a specified and reasonable time, the director will order forfeiture of all or that part of the owner/operator’s financial assurance instrument necessary to implement closure. Any owner/operator aggrieved by a forfeiture order may appeal as provided in section 260.235, RSMo.
AUTHORITY: sections 260.225, RSMo 2000 and 260.270, RSMo Supp. 2006.* Original rule filed April 16, 1997, effective Dec. 30, 1997. Amended: Filed Jan. 2, 2007, effective Sept. 30, 2007. *Original authority: 260.225, RSMo 1972, amended 1975, 1986, 1988, 1990, 1993, 1995 and 260.270, RSMo 1990, amended 1995, 2002, 2005.