Mo. Code Regs. Ann. tit. 10, § 60-13.025
PURPOSE: This rule establishes requirements for loans from state funding for financing construction improvements at public water systems.
(1) General Requirements.
(2) Eligible Projects and Project-Related Costs.
(3) Application Procedures.
(B) Applications are accepted year-round. Recipients shall provide—
ed by the department;
operator certified at the appropriate level, or expect to have prior to loan award;
emergency operating plan, or expect to have prior to loan award; and
the department to determine the recipient’s compliance history and technical, managerial, and financial capacity.
(4) Evaluation.
(5) Fees.
(7) Amortization Schedules. The following guidelines shall be used to establish amortization schedules under this rule:
(8) Requirements for Loan Recipients.
(B) Loan Closing. All documents and information must be submitted to the department in sufficient time to allow adequate time for review and must be approved sixty (60) days prior to the loan closing date established by the department. The department may extend deadlines if justified.
lowing documents must be submitted to and approved by the department:
rized representative by name. Recipients for assistance shall provide a resolution by the governing body designating a representative authorized to file the application for assistance, reimbursement requests, and act on behalf of the recipient in all matters related to the project;
following represents the minimum requirements for the project schedule:
date of issuance of notice to proceed;
described in this rule and the appropriate procurement documentation as described in paragraph (8)(G)1.;
specifications certified by a registered professional engineer licensed in Missouri;
property acquisition. Recipients of assistance shall have obtained title or option to the property or easements for the project prior to loan closing;
ordinances as described in this rule; and
tion deemed necessary by the recipient or the department to ensure the proper expenditure of loan funds.
tems. Prior to closing, if the project serves two (2) or more public water systems, the recipient shall submit executed agreements or contracts between the public water systems for the financing, construction, and operation of the proposed facilities.
3. User charge (water rate) ordinance.
maintain, for the useful life of the project, user charge ordinances approved by the department. User charge ordinances, at a minimum, shall be adopted prior to financing and implemented by the initiation of operation of the financed project.
designed to produce adequate revenues required for the operation and maintenance, including a reserve for equipment replacement. It shall be proportional and based upon actual use. A one hundred ten percent (110%) debt service reserve may be required. Each user charge system shall include an adequate financial management system that will accurately account for revenues generated by the system, debt service, and loan fee costs and expenditures for operation and maintenance, including replacement based on an adequate budget identifying the basis for determining the annual operation and maintenance costs and the costs of personnel, material, energy, and administration. The user charge system shall provide that the costs of operation and maintenance not directly attributable to users be distributed equally among the users. The system shall provide for an annual review of charges.
owned public water systems. Privately-owned public water systems must provide documentation from the Missouri Department of Economic Development showing an allocation under Missouri’s private activity bond cap and must obtain any necessary approvals from the Public Service Commission.
(C) Operation and Maintenance.
The recipient must make provision satisfactory to the department for assuring operational efficiency be achieved as quickly as possible and effective operation and maintenance of the constructed project throughout its design life. If required by the department, recipients will develop an operation and maintenance manual in accordance with departmental guidelines. A draft operation and maintenance manual must be submitted by construction completion.
completion, a start-up training proposal (if required) and proposed follow-up services contract must be submitted.
provision satisfactory to the department for assuring that operator(s) and maintenance personnel are hired in accordance with an approved schedule.
the department, one (1) year after initiation of operation of the constructed public water system, the recipient shall certify to the department whether or not the public water system meets the project performance standards. Any statement of noncompliance must be accompanied by a corrective action report containing an analysis of the cause of the project’s inability to meet performance standards, actions necessary to bring it into compliance, and reasonably scheduled date for positive certification of the project. Timely corrective action shall be executed by the recipient.
(D) Accounting and Audits. Recipients are required to have a dedicated source for repayment of any loans and an adequate financial management system and audit procedure for the project which provides efficient and effective accountability and control of all property, funds, and assets related to the project. The recipient’s financial system is subject to state or federal audits to assure fiscal integrity of public funds.
adequate accounting system for the project which provides efficient and effective accountability and control of all property, funds, and assets.
taining a financial management system which will adequately provide for an accurate, current, and complete disclosure of the financial results of each loan project. Accounting for project funds will be in accordance with generally accepted government accounting principles and practices, consistently applied, regardless of the source of funds.
includes books and records showing all financial transactions related to the construction project. The system must document all receipt and disbursement transactions and group them by type of account (for example, asset, revenue, expense, etc.) and by individual expense account (for example, personnel salaries and wages, subcontract costs, etc.). The recipient shall maintain books, records, documents and other evidence and accounting procedures and practices, sufficient to reflect properly the amount, receipt, and disposition by the recipient for all assistance received for the project and the total costs of the project of whatever nature incurred for the performance of the project for which the assistance was awarded.
(F) Minimum Requirements for Architectural or Engineering Contracts.
1. The agreement must—
ed to the accomplishment of the eligible project;
fee contract in the form of a bilaterally executed written agreement;
gift;
mance;
exceeded except by amendment; and
to be performed during construction should include, but not be limited to, the following:
tenance manual if required by the department that meets the requirements of this rule;
bids;
and analyzing construction bids and making recommendations for award;
ensure conformance with the construction contract documents unless waived by the department; and
assisting with facility operation for purposes of certifying that the facility is operating properly one (1) year after start-up.
neering contract must be submitted prior to the first reimbursement request.
(G) Procurement of Engineering Services.
shall be in accordance with sections 8.285 through 8.291, RSMo or subsection (8)(J) of this rule.
(H) Specifications. The construction specifications must contain the following:
specifications a clear and accurate description of the technical requirements for the material, product, or service to be procured. The description, in competitive procurement, shall not contain features which unduly restrict competition unless the features are necessary to test or demonstrate a specific thing or to provide for interchangeability of parts and equipment. The description shall include a statement of the qualitative nature of the material, product, or service to be procured and, when necessary, shall set forth those minimum essential characteristics and standards to which it must conform if it is to satisfy its intended use;
detailed product specifications if at all possible;
it is impractical or uneconomical to make a clear and accurate description of the technical requirements, recipients may use a brand name or equal description as a means to define the performance or other salient requirements of a procurement. The recipient need not establish the existence of any source other than the named brand. Recipients must state clearly in the specification the salient requirements of the named brand which must be met by offerers;
tion shall not require the use of structures, materials, equipment, or processes which are known to be available only from a sole source, unless the department determines that the recipient’s engineer has adequately justified in writing to the department that the proposed use meets the particular project’s minimum needs;
general use of experience clauses requiring equipment manufacturers to have a record of satisfactory operation for a specified period of time or of bonds or deposits to guarantee 10 CSR 60-13
replacement in the event of failure is restricted to special cases where the recipient’s engineer adequately justifies any such requirement in writing. Where this justification has been made, submission of a bond or deposit shall be permitted instead of a specified experience period. The period of time for which the bond or deposit is required shall not exceed the experience period specified;
requirements in accordance with sections 34.350–34.359, RSMo;
exceeding fifty thousand dollars ($50,000), the bid documents shall require each bidder to furnish a bid guarantee equivalent to five percent (5%) of the bid price. In addition, the bid documents must require the successful bidder to furnish performance and payment bonds, each of which shall be in an amount not less than one hundred percent (100%) of the contract price;
dance with sections 290.210-290.340, RSMo and 8 CSR 30 Chapter 3;
be provided for representatives of the department, the Environmental Improvement and Energy Resources Authority, and the Missouri State Auditor so they may have access to the work wherever it is in preparation or progress; and
owner shall make payment to the contractor in accordance with section 34.057, RSMo.”
(I) Construction Equipment and Supplies Procurement. This section describes the minimum procurement requirements which the recipient must use unless the recipient elects to use the design/build option described in subsection (8)(J) of this rule.
the procurement of materials, supplies, and services when the aggregate amount involved in any one (1) transaction does not exceed one hundred fifty thousand dollars ($150,000). The small purchase limitation of one hundred fifty thousand dollars ($150,000) applies to the aggregate total of an order, including all estimated handling and freight charges, overhead, and profit to be paid under the order. In arriving at the aggregate amount involved in any one (1) transaction, all items which should properly be grouped together must be included. Department concurrence and a minimum of three (3) quotes must be obtained prior to purchase.
applies to procurement of construction equipment, supplies, and construction services in excess of one hundred fifty thousand dollars ($150,000) awarded by the recipient. No contract shall be awarded until the department has approved the formal advertising and bidding.
A. Formal advertising.
recipient will cause adequate notice to be given of the solicitation by publication in newspapers of general circulation beyond the recipient’s locality (preferable statewide), construction trade journals or plan rooms, inviting bids on the project work and stating the method by which bidding documents may be obtained or examined.
bids. A minimum of thirty (30) days shall be allowed between the date when public notice, publication, insertion, or document availability in a plan room is first published and the date by which bids must be submitted. Bidding documents shall be available to prospective bidders from the date when the notice is first published or provided.
procedure.
reasonable number of bidding documents (Invitations for Bids) and shall furnish them upon request on a first-come, first-served basis. The recipient shall maintain a complete set of bidding documents and shall make them available for inspection and copying by any party. The bidding documents shall include, at a minimum:
work to be performed or equipment to be supplied and the required completion schedule;
the contract to be awarded;
method of bidding and the method of evaluation of bid prices and the basis and method for award of the contract or rejection of all bids;
and criteria which will be employed in evaluating bidders;
for bidding by sealed bid and for the safeguarding of bids received until public opening;
any part of the bidding documents during the period when bids are being prepared, addenda shall be communicated in writing to all firms which have obtained bidding documents in time to be considered before the bid opening time. All addenda must be approved by the department prior to award of the contract;
bid shall be allowed to modify or withdraw its bid before the time of bid opening;
for a public opening of bids at the place, date, and time announced in the bidding documents. Bids received after the announced opening time shall be returned unopened;
responsive, responsible bidder. After bids are opened, the recipient shall evaluate them in accordance with the methods and criteria set forth in the bidding documents. The recipient shall award contracts only to responsible contractors that possess the potential ability to perform successfully under the terms and conditions of a proposed contract. A responsible contractor is one that has financial resources, technical qualifications, experience, organization, and facilities adequate to carry out the contract or a demonstrated ability to obtain these. The recipient may reserve the right to reject all bids. Unless all bids are rejected for good cause, award shall be made to the lowest, responsive, responsible bidder. The recipient shall have established protest provisions in the specifications. These provisions shall not include the department as a participant in the protest procedures. If the recipient intends to make the award to a firm which did not submit the lowest bid, the recipient shall prepare a written statement before any award, explaining why each lower bidder was deemed nonresponsible or nonresponsive and shall retain the statements in its files. The recipient shall not reject a bid as nonresponsive for failure to list or otherwise indicate the selection of subcontractor(s) or equipment unless the recipient has clearly stated in the solicitation documents that the failure to list shall render a bid nonresponsive and shall cause rejection of a bid; and
with contract award must be obtained prior to actual contract award. Recipients shall notify the department, in writing, of each proposed construction contract which has an aggregate value over one hundred fifty thousand dollars ($150,000). The recipient shall notify the department within ten (10) calendar days after the bid opening for each construction subagreement. The notice shall include:
bidder that the recipient wishes to accept, including justification if the recommended successful bidder is not also the lowest bidder;
award;
previously and bidder acknowledgment of all addenda;
specifications;
bility worksheet and certification if bids exceed prebid estimates by more than fifteen percent (15%); and
previously submitted.
(K) Conflict of Interest.
recipient shall participate in the selection, award, or administration of a subagreement supported by state or federal funds if a conflict of interest, real or apparent, would be involved. This conflict would arise when—
the recipient, any member of their immediate families, or their partners have a financial or other interest in the firm selected for a contract; or
or has been awarded a subagreement employs, or is about to employ, any employee, officer or agent of the recipient, any member of their immediate families, or their partners.
or agents shall neither solicit nor accept gratuities, favors, or anything of substantial monetary value from contractors, potential contractors, or other parties to subagreements.
(L) Changes in Contract Price or Time. The contract price or time may be changed only by a change order. The value of any work covered by a change order or of any claim for increase or decrease in the contract price shall be determined by the methods set forth in the following:
1. Unit prices.
are acceptable for pricing changes of original bid items. However, when changes in quantities exceed fifteen percent (15%) of the original bid quantity and the total dollar change of that bid item is greater than twenty-five thousand dollars ($25,000), the recipient shall review the unit price to determine if a new unit price should be negotiated.
negotiated;
for labor, direct overhead, materials, supplies, equipment, and other services necessary to complete the work plus an amount to cover the cost of general overhead and profit.
(M) Progress Payments to Contractors.
progress payments to prime contractors and prime contractors should make prompt progress payments to subcontractors and suppliers for eligible construction, supplies, and equipment costs in accordance with section 34.057, RSMo.
The amount the recipient retains shall be in accordance with section 34.057, RSMo.
(N) Trustee or Paying Agent. The department may require the recipient to contract with a trustee or paying agent to provide the services listed below, along with other such services as detailed in the participant’s escrow agreement:
accounts for recipients;
ly payments from recipients; and
recipients.
(9) Reimbursement Terms.
(A) The maximum reimbursement will be no more than the sum of all eligible costs incurred to date. Each payment shall include the information listed here and any other information deemed necessary by the department to ensure proper project management and expenditure of public funds:
form;
the construction contractor, the recipient, and the consulting engineer, if applicable; and
equipment, and supplies for the project.
AUTHORITY: sections 640.100 and 640.140, RSMo 2016.* Original rule filed Jan. 19, 2001, effective Sept. 30, 2001. Amended: Filed June 13, 2018, effective Feb. 28, 2019. *Original authority: 640.100, RSMo 1939, amended 1978, 1981, 1982, 1988, 1989, 1992, 1993,1995, 1996, 1998, 1999, 2002, 2006, 2012, 2014 and 640.140, RSMo 1978.