Mo. Code Regs. Ann. tit. 10, § 60-13.010
PURPOSE: This rule establishes the department’s grant application procedures requirements and for construction of projects at public water supply districts and rural community water systems, and providing source water protection grants to support the Conservation Reserve Enhancement Program.
(2) Application Requirements.
(D) The grant application shall contain the following information:
study for the proposed project including, but not limited to, the following items: development and administration costs; land, structures, right-of-way costs; legal costs; engineering costs; interest costs; equipment costs; contingencies; other costs; and total project costs;
posed project which is in accordance with accepted engineering practices. The current “Design Guide for Community Water System” and “Ten State Standards” and applicable rules should be considered for design standards;
edness of the district or community, including: outstanding general obligation and revenue bonds; the purpose of each indebtedness; the amount of each indebtedness; the amortization period; the date payments are due; amount of installment; and the interest rate;
or community, including: the total assessed value of agricultural, commercial and industrial property, vacant lots and residential property; total annual revenue anticipated from this assessed property; water user charges; other sources of income available to finance the project; and cash on hand. The latest audit with an update would satisfy the requirements of this paragraph;
mine the cost per contracted connection;
of the residents in the district or community as determined in the latest federal census;
ratio of the contracted users to the potential users; and
nical, managerial, and financial (TMF) capacity on forms provided by the department. An applicant that does not meet the TMF capacity requirements established in 10 CSR 60-3.030 shall submit a plan outlining the steps the applicant will take to meet the requirements. The plan shall show the applicant will meet TMF requirements before the project is complete or within one (1) year of the award of the grant unless the department determines that a longer period of time is necessary.
(3) Grant Priorities.
tance. It is the intent of the department to maximize the effective use of state and federal grant and loan funds.
(4) Approval and Payment of Grants.
(B) Installment payments of the grant for construction projects shall be made at the request of the applicant and shall be based on expenditures outlined in paragraph (2)(E)1. of this rule. Payments will be made in equal installments as follows:
not less than twenty-five percent (25%) of the construction of the project is completed;
when not less than fifty percent (50%) of the construction of the project is completed;
when not less than seventy-five percent (75%) of the construction of the project is completed; and
after the project is completed, appropriate receipts and expenditures have been submitted and approved by the department, a consultant’s statement of work completion has been received, and a final inspection has been performed by department personnel and construction is approved by the department.
(6) Grants for Conservation Reserve Enhancement Program Participants.
(A) Program Description and Definition of Terms.
ment Program (CREP) is a state-federal partnership program targeted to address specific water quality, soil erosion and wildlife habitat issues related to agricultural use. The CREP uses financial incentives to encourage farmers to voluntarily enroll in contracts to remove lands from agricultural production and, instead, to implement approved conservation reserve practices.
tices in this program are: introduced grasses and legumes, native grasses, hardwood tree planting, wildlife habitat, contour grass strips, filter strips, riparian buffers, and wetland restoration.
under this section (6) is to provide an additional cash incentive (“rental enhancement payment”) to farmers to encourage participation in CREP. The rental enhancement payment is a per-acre cash payment to participating farmers for land enrolled in the CREP that is in addition to other payments or financial assistance from federal or state funds and is a percentage of the annual base rental payment.
average weighted soil rental rate for the three (3) predominant soil types on the acreage offered. The U.S. Department of Agriculture maintains this information on a county-bycounty basis for the entire country.
(B) Application Requirements.
RSMo, the applicant must first apply with the agency or other financial source which is to furnish the primary financial assistance. After the amount of that assistance has been determined, an application for a grant shall be submitted on forms provided by the department. The application shall be supported by the necessary documents and forms from other state and federal grant or lending agencies or private lending agencies to enable the department to establish eligibility and need for grant funds.
2. The application shall contain:
tected;
vation district approving the proposed practices to be implemented including a reasonable time line for completion;
and
farmer(s) (subrecipients) proposing the practices.
cation is submitted shall comply with appropriate state and local laws, rules and ordinances. These projects shall be limited to those areas with a source water protection program approved by the department.
ondary sources of funding and, as such, shall in no case exceed one thousand four hundred dollars ($1,400) per contracted connection, fifty percent (50%) of the total project cost, or five hundred thousand dollars ($500,000), whichever is less.
ment payment grant is expected.
enhancement payment grants not to exceed the product of five percent (5%) of the annual base rental payment times the duration of the contract in years (for example, if the contract is in effect fifteen (15) years, the rental enhancement grant would equal seventy-five percent (75%) of the total of all annual base rental payments), and expects this to be matched with an equal amount of other nonfederal funding.
those applicants that offer the highest percentage of matching funds. If matching funds are not available, the applicant may request a reduction or waiver of the match requirement, in which case the rental enhancement payment grant shall not exceed the product of ten percent (10%) of the annual base rental payment times the duration of the contract in years.
(C) Approval and Payment of Grants.
department when the grant application has been approved.
ent after completion of the approved practice. These grant payments shall be made immediately available to the farmer (subrecipient) implementing the practices. Grant payments to the recipient may be combined to cover multiple subrecipients.
AUTHORITY: section 640.615, RSMo 2000.* This rule was previously filed as 10 CSR 60- 2.020 Sept. 21, 1973, effective Oct. 1, 1973. Amended: Filed May 4, 1979, effective Sept. 14, 1979. Amended: Filed April 14, 1981, effective Oct. 11, 1981. Rescinded and readopted: Filed Feb. 2, 1983, effective July 1, 1983. Emergency amendment filed July 3, 1989, effective July 27, 1989, expired Nov. 23, 1989. Amended: Filed July 3, 1989, effective Nov. 23, 1989. Amended: Filed Jan. 19, 2001, effective Sept. 30, 2001. *Original authority: 640.615, RSMo 1989, amended 1999.