PURPOSE: This rule sets forth requirements for coal processing plants and support facilities not located at or near the mine site or not within the permit area for a mine, pursuant to section 444.810, RSMo.
- (1) Applicability. Each person who conducts surface coal mining and reclamation operations, which includes the operation of a coal processing plant or support facility which is not located within the permit area for a specific mine, shall obtain a permit to conduct those operations and comply with this rule.
- (2) Signs and markers for the coal processing plant, coal processing waste disposal area and water treatment facilities shall comply with 10 CSR 40-3.010.
- (3) Roads, transport and associated structures shall be constructed, maintained and reclaimed in accordance with 10 CSR 40-3.140(l)-(22).
- (4) Any stream or channel realignment shall comply with 10 CSR 40-3.040(4).
- (5) If required in the permit and plan, any disturbed area related to the coal processing plant or associated facilities shall have sediment control structures, in compliance with 10 CSR 40-3.040(5) and (6), and all discharges from these areas shall meet the requirements of 10 CSR 40-3.040(l) and (2) and any other applicable state or federal law.
- (6) Permanent impoundments associated with coal processing plants shall meet the requirements of 10 CSR 40-3.040(g) and (16). Dams constructed of or impounding coal processing ;“;;,““e shall comply with 10 CSR 40-3.080(9)-
- (7) Use of water wells shall comply with 10 CSR 40-3.040(13) and water rights shall be protected in accordance with 10 CSR 40-3.040(14).
- (8) Disposal of coal processing waste, solid waste and any excavated materials shall comply with 10 CSR 40-3.080(l), (7) and (8) and 10 CSR 40-3.060(l)-(4), respectively.
- (9) Discharge structures for diversions and sediment control structures shali comply with 10 CSR 40-3.040(7).
- (10) Air pollution control measures associated with fugitive dust emissions shall comply with 10 CSR 40-3.090.
- (11) Fish, wildlife and related environmental values shall be protected in accordance with 10 CSR 40.3.100(l)-(4).
- (12) Slide areas and other surface areas shall comply with 10 CSR 40.3.100(5).
- (13) Adverse effects upon or resulting from nearby underground coal mining activities shall be minimized by appropriate measures including, but not limited to, compliance with 10 CSR 40-3.040(15) and 10 CSR 40-3.070.
- (14) Reclamation shall include proper topsoil handling procedures, revegetation and abandonment in accordance with 10 CSR 40-3.060(16), 10 CSR 40-3.110(l)-(6), 10 CSR 40-3.120(l)-(7), 10 CSR 40-3.130 and 10 CSR 40-3.150(2)-(4).
- (15) Conveyors, buildings, storage bins or stockpiles, water treatment facilities, water storage facilities and any structures or system related to the coal processing plant shall comply with 10 CSR 40-3.
- (16) Any coal processing plant or associated structures located on prime farmland shall meet the requirements of 10 CSR 40-4.030. Auth: section 444.530, RSMo (1986).* Original rule filed Oct. 12,1979, effective Feb. 11,198O. ‘Original authority 1971, amended 1983,199O.