PURPOSE: This rule sets forth the requirements for review of the application, the approval and denial process and hearing requirements pursuant to section 444.773, RSMo.
(2) The director shall make a determination on an application within four (4) weeks after the public comment period provided in 10 CSR 40-10.020(2) expires. The recommendation will be to either issue or deny.
(A) The director shall make a recommendation on a permit application based on the following:
section 444.772, RSMo;
CSR 40-10.020;
ments received during the public notice period from persons who have a direct personal interest in one (1) or more of the factors the commission is required to consider in issuing a permit; and
mit revoked, a bond forfeited and has not 10 CSR 40-10
caused the revocation or forfeiture to be corrected to the satisfaction of the commission.
(3) The director may approve a variance to a permit application or permit amendment when the operation, reclamation or conservation plan deviates from the requirements of sections 444.760–444.790, RSMo and these rules if it can be demonstrated by the operator that—
(E) The procedure to be used in the review of a request for a variance shall be as follows:
the location of the area(s) that the variance request applies. Such map shall comply with the requirements of 10 CSR 40-10.020(2)(E); and
acres involved in the variance request area, the dates that work is to commence and is to be completed, and the nature of the variance request; and
AUTHORITY: sections 444.767, 444.772 and 444.784, RSMo Supp. 2004.* Original rule filed Aug. 2, 1991, effective Feb. 6, 1992. Amended: Filed June 1, 1994, effective Nov. 30, 1994. Amended: Filed April 1, 2004, effective May 30, 2005.
*Original authority: 444.767, RSMo 1971, amended 1990, 1993, 2001; 444.772, RSMo 1971, amended 1984, 1990, 1992, 2001; and 444.784, RSMo 1971, amended 1990, 2001.