Mo. Code Regs. Ann. tit. 10, § 26-2.082
PURPOSE: This rule lists the requirements for corrective action plans for cleanup of releases from underground storage tank sites.
PUBLISHER’S NOTE: The secretary of state has determined that the publication of the entire text of the material which is incorporated by reference as a portion of this rule would be unduly cumbersome or expensive. This material as incorporated by reference in this rule shall be maintained by the agency at its headquarters and shall be made available to the public for inspection and copying at no more than the actual cost of reproduction. This note applies only to the reference material. The entire text of the rule is printed here.
(1) Owners and operators are responsible for submitting a plan that provides for adequate protection of human health and the environment, as determined by the department, after fulfilling the requirements for release reporting and investigation in 10 CSR 26-2.071–10 CSR 26-2.074. Owners and operators must modify their plan as necessary to meet this standard.
(2) The department will approve the corrective action plan only after ensuring that implementation of the plan will adequately protect human health and safety and the environment. In making this determination the department should consider the following factors as appropriate:
(4) Owners and operators, in the interest of minimizing environmental contamination and promoting more effective clean-up, may begin clean-up of soil and groundwater before the corrective action plan is approved provided that they—
(5) Owners and operators shall follow a written procedure.
(B) For releases that occurred or were discovered prior to the effective date of this rule, owners and operators may use—
graph (5)(C)2. of this rule, provided—
rule, the owner or operator received the department’s written approval of a work plan for site characterization, risk assessment, or corrective action related to the release; and
or implemented the approved work plan within one (1) year of the date of the department’s approval of the plan or in accordance with a different schedule approved by the department;
graph (5)(C)1. of this rule; or
department, another written procedure.
(C) Written Procedures.
Action Process for Petroleum Storage Tanks guidance document, October 17, 2013, which is hereby incorporated by reference without any subsequent amendments or additions, and is published by the Department of Natural Resources, PO Box 176, Jefferson City, MO 65102-0176.
Action Process for Petroleum Storage Tanks, February 2004, as amended March 8, 2005, by Notice of Modifications to the Process and Interim Guidance Pertaining to Application of the New Soil Type Dependent Tier 1 Risk- Based Target Levels; the March 18, 2005, Soil Type Determination Guidelines; the March 3, 2005, Table 3-1 Default Target Levels; the April 2005 Table 4-1 Soil Concentration Levels to Determine the Need for Groundwater Evaluation During Tank Closure; the February 2005 Tables 7-1(a) through 7-12(c) Tier 1 Risk-Based Target Levels; and the April 21, 2005, Soil Gas Sampling Protocol, which are hereby incorporated by reference without any subsequent amendments or additions, and are published by the Department of Natural Resources, PO Box 176, Jefferson City, MO 65102-0176.
AUTHORITY: sections 319.109 and 319.137, RSMo Supp. 2013.* This rule originally filed as 10 CSR 20-10.066. Original rule filed April 2, 1990, effective Sept. 28, 1990. Amended: Filed Aug. 3, 1993, effective April 9, 1994. Moved and amended: Filed April 15, 2011, effective Dec. 30, 2011. Amended: Filed June 17, 2013, effective Feb. 28, 2014.
*Original authority: 319.109, RSMo 1989, amended 1995, 2004, 2008 and 319.137, RSMo 1989, amended 1993, 1995, 2004.