Mo. Code Regs. Ann. tit. 10, § 23-6.040
Construction Standards for Test Holes
Effective Jun 30, 1996sections 256.606 and 256.626, RSMo 1994.* Original rule filed Aug. 17, 1993, effective March 10, 1994. Amended: Filed Nov. 1, 1995, effective June 30, 1996Division of Geology and Land Survey
PURPOSE: This rule describes the minimum standards for a properly constructed test hole.
- (1) Standards for Construction of Test Holes. All test holes shall be constructed in a manner that will conserve and protect the groundwater resources and not be a source or channel of contamination or pollution to any aquifer.
- (2) Casing Material. All casing used in the construction of a test well must meet or exceed standards set out in 10 CSR 23-3.030.
- (3) Casing Depth. If permanent surface casing is set, it must be set at least fifty feet (50') into bedrock. Temporary surface casing lengths may be determined by the permitted contractor.
- (4) Temporary Cap. All holes must be capped during the period they remain unplugged.
- (5) Hole Size. Test hole size will be determined by the person owning the mineral rights or designing the hole.
- (6) Approved Grout. When a hole is grouted, procedures and materials set out in 10 CSR 23-3.030(3) and (4) must be followed. 10 CSR 23-6
AUTHORITY: sections 256.606 and 256.626, RSMo 1994.* Original rule filed Aug. 17, 1993, effective March 10, 1994. Amended: Filed Nov. 1, 1995, effective June 30, 1996.
*Original authority: 256.606, RSMo 1991 and 256.626, RSMo 1985, amended 1991.