Mo. Code Regs. Ann. tit. 10, § 20-8.120
PURPOSE: The following criteria have been prepared as a guide for the design of sewers. This rule is to be used with rules 10 CSR 20- 8.110 through 10 CSR 20-8.220 for the planning and design of the complete treatment facility. This rule reflects the minimum requirements of the Missouri Clean Water Commission in regard to adequacy of design, submission of plans, approval of plans, and approval of completed wastewater treatment facilities and collection systems. It is not reasonable or practical to include all aspects of design in these standards. The design engineer should obtain appropriate reference materials which include but are not limited to: copies of all ASTM International standards pertaining to sewers and appurtenances, design manuals such as Water Environment Federation’s Manuals of Practice, and other sewer design manuals containing principles of accepted engineering practice. Deviation from these minimum requirements will be allowed where sufficient documentation is presented to justify the deviation. These criteria are taken largely from the 2004 edition of the Great Lakes-Upper Mississippi River Board of State and Provincial Public 10 CSR 20-8
Health and Environmental Managers’ Recommended Standards for Wastewater Facilities and are based on the best information presently available. These criteria were originally filed as 10 CSR 20-8.030. It is anticipated that they will be subject to review and revision periodically as additional information and methods appear.
(1) Definitions. Definitions as set forth in the Clean Water Law and 10 CSR 20-2.010 shall apply to those terms when used in this rule, unless the context clearly requires otherwise. Where the terms “shall” and “must” are used, they are to mean a mandatory requirement insofar as approval by the Missouri Department of Natural Resources (department) is concerned, unless justification is presented for deviation from the requirements. Other terms, such as “should,” “recommend,” “preferred,” and the like, indicate the preference of the department for consideration by the design engineer.
(4) Design Capacity and Design Flow.
(5) Details of Design and Construction.
(D) Slope.
structed to give mean velocities, when flowing full, of not less than two feet (2') per second (0.6 m/s). The following are the minimum slopes which should be provided for sewers forty-two inches (42") (107 cm) or less; however, slopes greater than these may be desirable for construction, to control sewer gases, or to maintain self-cleansing velocities at all rates of flow within the design limits: 42 inch (107 cm) 0.037
above table should be designed and constructed to give mean velocities, when flowing full, of not less than three feet (3') per second (0.9 m/s), based on Manning’s formula using an “n” value of 0.013.
are slightly less than the recommended minimum slopes may be permitted. Such decreased slopes may be considered where the depth of flow will be one-third (1/3) of the diameter or greater for design average flow. Whenever decreased slopes are selected, the design engineer must furnish with his/her engineering report or facility plan computations of the anticipated flow velocities of average daily and peak hourly flow rates. The operating authority of the sewer system will give written assurance to the department that any additional sewer maintenance required by reduced slopes will be provided.
diameter and slope shall be selected to obtain the greatest practical velocities to minimize settling problems. Oversize sewers will not be approved to justify using flatter slopes. If the proposed slope is less than the minimum slope of the smallest pipe, which can accommodate the design peak hourly flow, the actual depths and velocities at minimum, average, and design maximum day and peak hourly flow for each design section of the sewer shall be calculated by the design engineer and be included with the plans.
shall be laid with uniform slope between manholes. cm) or less shall be laid with straight alignment between manholes. Straight alignment shall be checked by either using a laser beam or lamping.
er than twenty-four inches (24") (61 cm) may be considered on a case-by-case basis provided compression joints are specified and ASTM or specific pipe manufacturers’ maximum allowable pipe joint deflection limits are not exceeded. Curvilinear sewers shall be limited to simple curves which start and end at manholes. When curvilinear sewers are proposed, the recommended minimum slopes indicated in paragraph (5)(D)1. of this rule must be increased accordingly to provide a minimum velocity of two feet (2') per second (0.6 m/s) when flowing full.
(F) Changes in Pipe Size.
one, a manhole is required according to subparagraph (6)(A)1.B. of this rule. The invert of the larger sewer should be lowered sufficiently to maintain the same energy gradient. An approximate method for securing these results is to place the 0.8 depth point of both sewers at the same elevation.
for projected flows. When the diameter of the receiving sewer is less than the diameter of the proposed extension at a manhole, the manhole shall be constructed with special consideration of an appropriate flow channel to minimize turbulence. The department may require a schedule for construction of future downstream sewer relief.
| E. Location of wastewater treatment | or equal, spaced as follows: | ||
|---|---|---|---|
| 15 inch (38 cm) | 0.15 | ||
| facilities; | A. Not over thirty-six feet (36') (11 | ||
| F. Depth of excavation; and | 16 inch (41 cm) | 0.14 | m) center-to-center on grades twenty percent |
| G. Pumping requirements. | 18 inch (46 cm) | 0.12 | (20%) and up to thirty-five percent (35%); |
| 2. The basis of design for all sewer pro- | 21 inch (53 cm) | 0.10 | B. Not over twenty-four feet (24') |
| jects shall be included in the engineering | (7.3 m) center-to-center on grades thirty-five | ||
| 24 inch (61 cm) | 0.08 | ||
| report or facility plan. More detailed compu- | percent (35%) and up to fifty percent (50%); | ||
| tations may be required by the department for | 27 inch (69 cm) | 0.067 | and |
| critical projects. | 30 inch (76 cm) | 0.058 | C. Not over sixteen feet (16') (4.9 m) |
| (B) Sewer flows shall be based on the | 33 inch (84 cm) | 0.052 | center-to-center on grades fifty percent |
| design peak hourly flow in accordance with | (50%) and over. | ||
| 36 inch (91 cm) | 0.046 | ||
| 10 CSR 20-8.110(4)(C)4. and must be | (E) Alignment. | ||
| designed to prevent or eliminate sanitary | 39 inch (99 cm) | 0.041 | 1. Sewers twenty-four inches (24") (61 |
| 1. The following factors must be consid- | Minimum Slope in | 5. High velocity protection. Where | |
|---|---|---|---|
| ered in determining the required capacities of | Nominal Sewer | Feet Per 100 Feet | velocities greater than fifteen feet (15') per |
| sanitary sewers: | Size | (m/100 m) | second (4.6 m/s) are attained, special provi- |
| A. Design peak hourly flow; | 8 inch (20 cm) | 0.40 | sion shall be made to protect against dis- |
| B. Additional maximum wastewater | placement by erosion and impact. | ||
| 10 inch (25 cm) | 0.28 | 6. Steep slope protection. Sewers on | |
| or waste flow from industrial plants; | |||
| C. Inflow and infiltration (I/I); | 12 inch (30 cm) | 0.22 | twenty percent (20%) slope or greater shall |
| D. Topography of area; | 14 inch (36 cm) | 0.17 | be anchored securely with concrete anchors |
soil characteristics, exceptionally heavy external loadings, abrasion, corrosion, and similar problems.
shall conform to the appropriate ASTM specifications.
ASTM specifications shall be used for joining dissimilar materials. The leakage limitations on these joints shall be in accordance with paragraph (5)(I)4. or (5)(I)5. of this rule.
vent damage from superimposed live, dead, and frost-induced loads. Proper allowance for loads on the sewer shall be made because of soil and potential groundwater conditions, as well as the width and depth of the trench. Where necessary, special bedding, haunching, initial backfill, concrete cradle, or other special construction shall be used to withstand anticipated potential superimposed loading or loss of trench wall stability. See ASTM D2321 or ASTM C12 when appropriate.
which ASTM standards have not been established, the design engineer shall provide complete material and installation specifications developed on the basis of criteria adequately documented and certified in writing by the pipe manufacturer to be satisfactory for the specific detailed plans for approval by the department.
(H) Installation.
shall contain appropriate requirements based on the criteria, standards, and requirements established by industry in its technical publications. Requirements shall be set forth in the specifications for the pipe and methods of bedding and backfilling thereof so as not to damage the pipe or its joints, impede cleaning operations, and future tapping, nor create excessive side fill pressures and ovalation of the pipe, nor seriously impair flow capacity.
2. Trenching.
ample to allow the pipe to be laid and jointed properly and to allow the bedding and haunching to be placed and compacted to adequately support the pipe. The trench sides shall be kept as nearly vertical as possible. When wider trenches are specified, appropriate bedding class and pipe strength shall be used.
the size and stiffness of the pipe, stiffness of the embedment, insitu soil, and depth of cover shall be considered in determining the minimum trench width necessary to adequately support the pipe.
stones shall be removed to provide a minimum clearance of four inches (4") (10 cm) below and on each side of all pipe(s).
excavations or other parts of the work shall be removed until all the work has been completed. No sanitary sewer that ultimately arrives at existing pumping stations or wastewater treatment facilities shall be used for the disposal of trench water.
fill.
C, or crushed stone, as described in ASTM C12, shall be used and carefully compacted for all rigid pipe provided the proper strength pipe is used with the specified bedding to support the anticipated load based on the type of soil encountered and potential groundwater conditions.
materials for bedding and initial backfill, as described in ASTM A746 for Type 1 through Type 5 laying conditions, shall be used for ductile iron pipe provided the proper strength pipe is used with the specified bedding to support the anticipated load based on the type of soil encountered and potential groundwater conditions.
for bedding, haunching, and initial backfill, Classes I, II, or III, as described in ASTM D2321, shall be used and carefully compacted for all flexible pipe provided the proper strength pipe is used with the specified bedding to support the anticipated load based on the type of soil encountered and potential groundwater conditions.
described in ASTM D2680, the bedding, haunching, and initial backfill requirements for composite pipe shall be the same as for plastic pipe.
4. Final backfill.
material removed from excavation except where other material is specified. Debris, frozen material, large clods, stones, organic matter, or other unstable materials shall not be used for final backfill within two feet (2') (0.6 m) of the top of the pipe.
such a manner as not to disturb the alignment of the pipe.
5. Deflection test.
on all flexible pipe. The test shall be conducted after the final backfill has been in place at least thirty (30) days to permit stabilization of the soil-pipe system.
five percent (5%). If the deflection exceeds five percent (5%), the pipe shall be excavated. Replacement or correction shall be accomplished in accordance with requirements in the department-approved specifications.
the deflection test shall have a diameter not less than ninety-five percent (95%) of the base inside diameter or average inside diameter of the pipe depending on which is specified in the ASTM specification, including the appendix, to which the pipe is manufactured. The test shall be performed without mechanical pulling devices. A mandrel must have nine (9) or more odd number of flutes or points.
all new and rehabilitated sewers after installation is recommended.
(I) Joints and Infiltration.
the materials used shall be included in the specifications. Sewer joints shall be designed to minimize infiltration and to prevent the entrance of roots throughout the life of the system.
tions to the sewer main shall be watertight and not protrude into the sewer. If a saddletype connection is used, it shall be a device designed to join with the types of pipe which are to be connected. All materials used to make service connections shall be compatible with each other and with the pipe materials to be joined and shall be corrosion proof.
specified. This may include appropriate water or low pressure air testing. The testing methods selected should take into consideration the range in groundwater elevations during the test and anticipated during the design life of the sewer.
exfiltration or infiltration shall not exceed one hundred (100) gallons per inch of pipe diameter per mile per day (0.38 m3/cm of pipe diameter/km/day) for any section between manholes of the system. An exfiltration or infiltration test shall be performed with a minimum positive head of two feet (2') (0.6 m).
mum, conform to the test procedure described in ASTM C828 for clay pipe, ASTM C924 for concrete pipe twenty-four inches (24") or less in diameter, ASTM C1103 for concrete pipe twenty-seven inches (27") or greater in diameter, and ASTM F1417 for plastic, composite, and ductile iron pipe. All other materials shall have test procedures approved by the department.
(6) Manholes.
(A) Location.
1. Manholes shall be installed—
alignment;
hundred feet (400') (120 m) for sewers fifteen inches (15") (38 cm) or less; and
hundred feet (500') (150 m) for sewers sixteen inches to thirty inches (16"–30") (46 cm–76 cm).
hundred feet (500') (150 m) may be approved by the department in cases where adequate cleaning equipment can justify such spacing.
larger sewers.
cial conditions and shall not be substituted for manholes nor installed at the end of laterals greater than one hundred fifty feet (150') (46 m) in length.
(B) Drop Type.
sewer entering a manhole at an elevation of twenty-four inches (24") (61 cm) or more above the manhole invert. Where the difference in elevation between the incoming sewer and the manhole invert is less than twentyfour inches (24") (61 cm), the invert shall be filleted to prevent solids deposition.
with outside drop connection. Inside drop connections can be used when the manhole diameter is sufficient to secure the drop pipe to the interior wall of the manhole and provide adequate access for cleaning.
connections must not enter the manhole at a joint.
that would result from the backfilling operation in the vicinity of the manhole, the entire outside drop connection shall be encased in concrete.
(D) Flow Channel.
manhole should be made to conform as closely as possible in shape and slope to that of the connecting sewers, without obstructing maintenance, inspection, or flow in the sewers.
ified in manholes, including branch inlets, minimum slopes indicated in paragraph (5)(D)1. of this rule should be increased to maintain acceptable velocities.
(F) Watertightness.
holes shall be of the precast concrete or poured-in-place concrete type. Precast manholes shall conform to the design and test methods specified in ASTM C478 and C497.
rings, precast section joints, and any additional areas potentially subject to infiltration shall be sealed watertight.
to the manhole with a gasketed flexible watertight connection or any watertight connection arrangement that allows differential settlement of the pipe and manhole wall to take place.
used wherever the manhole tops may be flooded by street runoff or high water. Boltdown cover assemblies may be needed on manholes subject to displacement by sewer surcharging. Locked manhole covers may be desirable in isolated easement locations or where vandalism may be a problem.
(G) Inspection and Testing. The specifications shall include a requirement for inspection and testing for watertightness or damage prior to placing into service.
crete sewer manholes, shall conform to the test procedures in ASTM C1244 or the manufacturer’s recommendation.
concrete sewer manholes, shall conform to the test procedures in ASTM C969.
(8) Sewers in Relation to Streams.
(A) Location of Sewers in Streams.
entering or crossing streams shall be at a sufficient depth below the natural bottom of the stream bed to protect the sewer line. In general, the following cover requirements must be met:
required where the sewer is located in rock;
required in other material. In major streams, more than three feet (3') (0.9 m) of cover may be required;
of the sewer line should be placed below the bottom of the channel pavement; and
the proposed sewer crossing will not interfere with future modifications to the stream channel. Justification for requesting less cover shall be provided to the department.
streams shall be located sufficiently outside the stream bed to prevent pollution by siltation during construction and to minimize possible exposure due to erosion.
walls, manholes, gateboxes, or other structures shall be located so they do not interfere with the free discharge of flood flows of the stream.
should be designed to cross the stream as nearly perpendicular to the stream flow as possible and shall be free from change in grade.
minimize the number of stream crossings.
(B) Construction.
ing streams shall be constructed of ductileiron pipe with mechanical joints; otherwise, they shall be constructed so they will remain watertight and free from changes in alignment or grade. Material used to backfill the trench shall be stone, coarse aggregate, washed gravel, or other materials which will not readily erode, cause siltation, damage pipe during placement, or corrode the pipe.
methods that will minimize siltation and erosion shall be employed. The design engineer shall include in the project specifications the method(s) to be employed in the construction of sewers in or near streams. Such methods shall provide adequate control of siltation and erosion by limiting unnecessary excavation, disturbing or uprooting trees and vegetation, dumping of soil or debris, or pumping siltladen water into the stream. Specifications shall require that clean-up, grading, seeding, planting, or restoration of all work areas shall begin immediately. Exposed areas shall not remain unprotected for more than seven (7) days.
(9) Aerial Crossings.
(10) Protection of Water Supplies.
(B) Relation to Water Works Structures.
made to cover all conditions, it is recognized that sewers shall meet the requirements of 10 CSR 23-3.010 with respect to minimum distances from public water supply wells or other water supply sources and structures.
as basins, wells, or other treatment units, within two hundred feet (200') (60 m) of the proposed sewer shall be shown on the engineering plans.
(C) Relation to Water Mains.
1. Horizontal and vertical separation.
ten feet (10') (3.0 m) horizontally from any existing or proposed water main. The distances shall be measured edge-to-edge. In cases where it is not practical to maintain a ten-foot (10') (3.0 m) separation, the department may allow deviation on a case-by-case basis, if supported by data from the design engineer. Such a deviation may allow installation of the sewer closer to a water main, provided that the water main is in a separate trench or on an undisturbed earth shelf located on one (1) side of the sewer and at an elevation so the bottom of the water main is at least eighteen inches (18") (46 cm) above the top of the sewer.
horizontal and vertical separation as described above for sewers, the sewer must be constructed of slip-on or mechanical joint pipe or continuously encased and be pressure tested to one hundred fifty pounds per square inch (150 psi) (1,034 kPa) to assure watertightness.
least ten feet (10') (3.0 m) horizontally from any existing or proposed water main.
2. Crossings.
be laid to provide a minimum vertical distance of eighteen inches (18") (46 cm) between the outside of the water main and the outside of the sewer. This shall be the case where the water main is either above or below the sewer. The crossing shall be arranged so that the sewer joints will be equidistant and as far as possible from the water main joints. Where a water main crosses under a sewer, adequate structural support shall be provided for the sewer to maintain line and grade.
proper vertical separation as stipulated above, one (1) of the following methods must be specified:
constructed equal to water pipe and shall be pressure tested to assure watertightness prior to backfilling; or
line may be continuously encased or enclosed in a watertight carrier pipe which extends ten feet (10') (3.0 m) on both sides of the crossing, measured perpendicular to the water main. The carrier pipe shall be of materials 10 CSR 20-8
approved by the department for use in water main construction.
AUTHORITY: section 644.026, RSMo 2000.* Original rule filed Aug. 10, 1978, effective March 11, 1979. Amended: Filed May 17, 1994, effective Dec. 30, 1994. Amended: Filed June 28, 2011, effective Feb. 29, 2012. *Original authority 1972, amended 1973, 1987, 1993, 1995.