Mo. Code Regs. Ann. tit. 10, § 100-5.010
PURPOSE: This rule describes who can make claims against the Petroleum Storage Tank Insurance Fund, when and how such claims must be made, requirements to seek preapproval of costs, what costs the fund considers eligible, and how to request payment from the fund.
(1) A notice of claim must be submitted in writing to the board as soon as reasonably possible after a fund participant or beneficiary described in section (4) of this rule:
(2) Except as described below, prior to the initiation of any work where cleanup costs will be incurred, whether within the deductible or in excess of the deductible, the cleanup costs must first be approved by the board. Failure to obtain approval of the cleanup costs may subject the fund participant or fund beneficiary to reduction or denial of benefits.
(4) Fund participants or beneficiaries may request pre-approval and reimbursement of costs from the fund—
(A) For a release that occurs or is discovered on a date that the participant is participating in the fund.
notice of claim to the board while the participant is insured and before expiration or cancellation of the participant’s coverage, or during an extended reporting period granted by the board under 10 CSR 100-4.010 or 10 CSR 100-4.020.
costs approved in advance, as described in this rule.
made a claim may request that the board assign his or her benefits for cleanup costs to another party, and the board may, with the consent of the other party and at the board’s sole discretion, agree to such assignment;
(B) For a site where one (1) or more petroleum storage tank(s) was/were in use on December 31, 1997, the owner or operator applied to participate in the fund by December 31, 1997, that application was ultimately accepted by the board, there are ongoing costs of cleanup associated with a release from one (1) or more of those tanks which occurred prior to the date the application was accepted, and the cleanup began after August 28, 1989.
costs approved in advance, as described in this rule.
eligible site, the owner or operator of any petroleum storage tanks at the site must maintain participation in the fund as long as such tanks are in use. Failure to do so shall result in the site becoming ineligible; costs incurred after the date of cancellation or nonrenewal of participation in the fund are not eligible. Should the owner or operator elect to participate in the fund again, he or she may become eligible under subsection (4)(A) for any new release;
(C) For a site where a release occurred as a result of the operation of one (1) or more petroleum storage tanks, cleanup began or will begin after August 28, 1989, and the tank(s) from which the release occurred was/were taken out of use prior to December 31, 1997, provided such site was documented by or reported to the Department of Natural Resources prior to December 31, 1997.
evidence of a site being documented by or reported to the Department of Natural Resources may include, but is not limited to:
form;
form circulated by the Department of Natural Resources in 1995–1997;
overnight delivery service, identifying the location of the site and indicating the existence or prior existence of tanks on the site;
facsimile, identifying the location of the site and indicating the existence or prior existence of tanks on the site;
lar report, submitted to the department, identifying the site as one where tanks were previously operated; or
which is determined by the board to provide reasonable evidence of such fact.
by the board to provide evidence that the site was documented by or reported to the Department of Natural Resources prior to December 31, 1997.
costs approved in advance, as described in this rule;
(D) For a site described in subsection (4)(B) or (4)(C), except the release occurred and was being remediated prior to August 28, 1989.
must get cleanup costs approved in advance, as described in this rule; and
(E) For a site where underground storage tanks which contained petroleum were taken out of use prior to December 31, 1985, and the current owner purchased such site before December 31, 1985, provided such site was reported to the board on or before June 30, 2000. For the purposes of this subsection, current owner shall mean the person who owns a site at the time it is reported to the Petroleum Storage Tank Insurance Fund Board of Trustees or its designated representative.
costs approved in advance, as described in this rule.
(5) Fund participants or beneficiaries may not receive monies from the fund for the following sites:
(B) Sites contaminated by a release from a tank that—
stances when the release occurred;
thousand one hundred (1,100) gallons or less, which is used for storing motor fuel for noncommercial purposes;
release, for storing heating oil for consumptive use on the premises;
water or waste water collection system;
such as a basement, the tank is on or above the floor; or
er, or similar electrical equipment; and
(6) The following persons may request preapproval of costs and reimbursement from the fund:
(8) Fund participants and beneficiaries who desire reimbursement from the fund are required to seek preapproval of cleanup costs by following the procedures outlined below:
(A) Tank Removal—Prior to removal of a petroleum storage tank or other activity involving excavation of contaminated soil, a fund participant or beneficiary must—
proposals from qualified contractors or consultants to demonstrate that a fair and reasonable price will be paid. The bids or cost estimates must include all tasks and services which may be necessary and an anticipated schedule for the tasks; and
board, including:
hauling of contaminated soil, expressed as a unit cost (e.g., per ton or per cubic yard);
treatment of contaminated soil;
expressed as a unit cost;
ment, and/or disposal of contaminated water which may be encountered during the excavation;
agement, supervision, and reporting;
and/or analysis of soil and water samples;
expressed as unit costs, for any additional costs which may be incurred if field conditions warrant or necessitate more work than anticipated; and
anticipated cleanup costs;
(B) Site Characterization—Prior to conducting a site characterization which is required in response to a release, a fund participant or beneficiary must—
proposals from qualified contractors or consultants to demonstrate that a fair and reasonable price will be paid and submit the bid(s) or proposal(s) to the board. The bids or cost estimates must include:
vices which may be necessary;
regarding the current and reasonably anticipated future uses of potentially-impacted properties;
events;
ties, with drilling quoted on a per lineal foot basis;
ysis of soil and/or water samples, as appropriate;
agement, oversight, data analysis, reporting, and similar activities, as appropriate;
expressed in unit costs, for additional costs which may be incurred if field data indicates the need for expanded field investigation; and
ipated costs associated with the site characterization;
(C) Risk Assessment.
a fund participant or beneficiary must submit one (1) or more cost estimate(s) to the board.
the anticipated schedule of events and/or tasks.
bined with a cost estimate for site characterization.
costs for both a Tier 1 and a Tier 2 risk assessment.
costs for preparation of a corrective action plan.
ipant or beneficiary to submit a cost estimate Board of Trustees
for a Tier 2 or Tier 3 risk assessment.
(D) Corrective Action.
in response to a release, a fund participant or beneficiary must obtain an adequate number of bids or proposals, each of which must include a schedule, from qualified contractors or consultants to adequately compare costs of alternatives for achieving the applicable corrective action standards. These proposals may include:
tions, removal, or remediation of chemicals of concern;
plete exposure pathways;
a fund participant or beneficiary must submit the bid(s) or proposal(s) to the board.
lease or purchase and installation of equipment designed to clean up petroleum contamination, the fund participant or beneficiary is required to solicit competitive bids for such equipment and provide such bids to the board. A fund participant or beneficiary who is paid salvage value for remediation equipment after corrective action is completed shall report such to the board, which will reduce its reimbursement for decommissioning and removal of said remediation equipment by that amount.
(F) If the bid(s) or cost estimate(s) submitted to the board are incomplete, or contain costs which are higher than the board determines to be reasonable, the board may—
ry to solicit additional cost estimates; or
ry to demonstrate how the estimate was prepared.
(9) The board will recognize eligible, reasonable, and necessary costs incurred for the following activities:
(10) Costs not associated with cleanup of a release from a petroleum storage tank are not eligible. Such costs include, but are not limited to:
(D) Costs of excavation, transport, treatment or disposal of soil which is not contaminated with petroleum at levels such that the Department of Natural Resources requires corrective action, except that—
similar surface material, overburden, or fill material which is necessary to access contaminated soil for removal is eligible; and
disposal of backfill which surrounds underground tanks or piping, which is removed during tank closure activities, and which is contaminated at a level such that the Department of Natural Resources prohibits placement of the material back into the excavated area, are eligible;
(11) The board shall have the authority to investigate as needed in response to the submission of a notice of claim or invoices.
(A) The board shall have the right, but not the obligation, to—
the fund participant or beneficiary has given notice of claim;
ing the operation of tanks at the site, maintenance of the tank system, site characterization, or corrective actions; or
owners, operators, their employees, contractors, consultants, local officials, or other persons with pertinent knowledge or information about a claim.
(12) When a fund participant or beneficiary incurs costs for cleanup of petroleum contamination, he or she shall comply with the procedures set forth below to request reimbursement from the fund:
(A) Persons requesting reimbursement from the fund must send invoices for the work done, along with a copy of any reports generated by consultants, contractors, or laboratories as part of the work, to the address specified by the board.
within two (2) years of the date the costs were incurred. Failure to submit invoices within that time frame shall waive the fund participant’s or beneficiary’s rights, and those of their successors and assigns, to any benefits which would have otherwise been paid by the Petroleum Storage Tank Insurance Fund Board of Trustees for such costs.
photocopies are submitted, they must be accompanied by a signed statement certifying 10 CSR 100-5
that the copies are true and accurate.
mat of the previously-submitted cost estimate;
AUTHORITY: sections 319.129 and 319.131, RSMo 2016.* Original rule filed April 1, 1999, effective Nov. 30, 1999. Amended: Filed March 31, 2000, effective Sept. 30, 2000. Amended: Filed Nov. 15, 2001, effective May 30, 2002. Amended: Filed Aug. 1, 2014, effective March 30, 2015. Amended: Filed Feb. 15, 2018, effective Sept. 30, 2018.
*Original authority: 319.129, RSMo 1989, amended 1991, 1996, 1998, 2001, 2008 and 319.131, RSMo 1989, amended 1991, 1994, 1995, 1996, 1998, 1999, 2001, 2008.