Mo. Code Regs. Ann. tit. 1, § 30-3.050
Project Payments, Acceptance and Occupancy PURPOSE: This rule establishes the procedures for payments, acceptance and occupancy of projects. (1) Payments. Payments shall be made after review and verification of work and materials in place and/or on-site. Review and verification shall be accomplished as part of the periodic construction progress meeting. Apparent differences between the requests for payment and work or material shall be resolved in order that the request for payment may be signed by the construction manager, contractor and designer prior to conclusion of the progress meeting. The contractor’s request for payment shall be transmitted expeditiously to the Division of Facilities Management, Design and Construction. Administrative processing and approval in the Office of Administration shall be completed within fifteen (15) working days after receipt by the director of the payment request. When required, the payment request shall be transmitted to the department/agency. Signature for the department/agency and return to the Division of Facilities Management, Design and Construction shall be accomplished by the department/agency within five (5) working days after receipt of the payment request.
Effective Jun 30, 2008sections 8.310 and 8.320, RSMo 2000.* Original rule filed July 9, 1981, effective Feb. 15, 1982. Emergency amendment filed June 14, 1985, effective July 1, 1985, expired Oct. 29, 1985. Amended: Filed June 14, 1985, effective Aug. 26, 1985. Rescinded and readopted: Filed Nov. 5, 2007, effective June 30, 2008Division of Facilities Management, Design and Construction
- (A) Projects Costing One Hundred Thousand Dollars ($100,000) or More. Payment for labor and material on projects costing one hundred thousand dollars ($100,000) or more shall be made in accordance with section 8.260, RSMo Supp. 2007. Requests for payments shall be submitted in the form and be supported by documentation as may be required by the director. When more than one (1) payment is made on those projects, the contractor shall furnish a payment certificate with the second and succeeding payment requests. The certificate shall affirm that subcontractors and suppliers have been paid in proportion to the work and materials paid for on previous payment requests.
- (B) Projects Costing Less Than One Hundred Thousand Dollars ($100,000). Payment for labor and materials on projects costing less than one hundred thousand dollars ($100,000) shall be made in accordance with section 8.270, RSMo Supp. 2007. Requests for payment shall be submitted in the form and be supported by documentation as required by the director.
- (C) Final Payment. Final payment shall not be made until all work under the contract has been completed and accepted, documentation as required by the director has been furnished and project records have been delivered to the construction manager. The contractor shall provide releases from all subcontractors and suppliers or a letter of release from the surety holding the performance and payment bond evidencing that they have been paid in full or covered by the bond provisions. After review and approval of the requests for payment, reports, records and other documentation by the director or his/her designee, final payment may be made. Administrative processing of final payment in the Office of Administration shall be completed within fifteen (15) working days after receipt by the director of completed documentation and final payment request.
- (D) Projects Supported with Non- Appropriated Funds. All payments for projects supported directly with donated, grant or other funding not appropriated by the general assembly shall be made in accordance with agreements established in the initial coordination and after approval of the director or his/her designee.
(2) Acceptance and Occupancy.
- (A) Acceptance. After completion of all work (including deficiencies or discrepancies noted in the final inspection) and delivery of project records, the director or his/her designee shall issue final payment acknowledging acceptance of the project.
- (B) Occupancy. The employees of the department/agency shall not occupy the facility or area where the project work is performed until after acceptance by the director. In exceptional circumstances, the director may establish conditions for occupancy prior to final acceptance.
- (C) Project Records. The construction manager/project manager shall deliver one
(1) copy of project shop drawings, operation and maintenance manuals, record drawings, warranties and all other pertinent files to a representative of the department/agency. The department/agency shall cause these records to be preserved and stored at the project site or other suitable location. Those records shall be readily available for reference in maintenance, repair and future work at the site.
- (D) Reporting Changes in Facility Conditions. The department/agency as part of the periodic facility inspection process shall report any substantive change in condition of the facility to the director. Substantive changes in condition of the facility resulting from accidents, acts of God or other causes shall be reported to the director at the time of occurrence.
(3) Exemptions. There are specific exemptions from requirements of this rule provided by the Missouri Constitution or by statute.
- (A) Department of Transportation projects and expenditures for highway construction and highway maintenance are exempt from the provisions of this rule by Article IV, Section 29, Missouri Constitution of 1945.
- (B) Institutions of higher learning, community junior colleges and the Department of Conservation are exempted by section 8.310, RSMo from provisions of this rule which requires coordination with or approval by the commissioner of administration, or both Division of Facilities Management, Design and Construction for approval of payments.
- (4) This rule becomes effective with the appropriation for the upcoming fiscal year.
AUTHORITY: sections 8.310 and 8.320, RSMo 2000.* Original rule filed July 9, 1981, effective Feb. 15, 1982. Emergency amendment filed June 14, 1985, effective July 1, 1985, expired Oct. 29, 1985. Amended: Filed June 14, 1985, effective Aug. 26, 1985. Rescinded and readopted: Filed Nov. 5, 2007, effective June 30, 2008.
*Original authority: 8.310, RSMo 1958, amended 1965, 1984, 1987, 1995 and 8.320, RSMo 1958, amended 1965.