Mo. Code Regs. Ann. tit. 1, § 30-3.040
PURPOSE: This rule establishes the procedures for accomplishing the work on Capital Improvements and Maintenance Projects.
(1) Bidding.
Division of Facilities Management, Design and Construction prior to initiating any purchasing procedures. This coordination is essential to assure that the facility can accommodate the equipment.
five thousand dollars ($25,000). Contracts costing more than twenty-five thousand dollars ($25,000) will have solicitation advertised in accordance with section 8.250, RSMo Supp. 2007. In addition, when appropriate, individual firms shall be contacted to determine their interest and/or solicit their interest.
dollars ($25,000) or less. Projects costing twenty-five thousand dollars ($25,000) or less will be referred to in these regulations as small projects. Small projects may be accomplished through the use of standing maintenance contracts in accordance with 1 CSR 30-4.030(3) or they may be individually procured by the agency in accordance with these instructions and, when appropriate, the current policies of the Division of Purchasing. They may be funded from operations appropriations or non-appropriated funds following these procedures.
repair projects, firms that are available and competent to perform required work will be invited to visit the site for examination and discussion of the work. Attending firms will be provided with available drawings, specifications, proposal forms and instructions for submitting proposals. Telephone bids for an hourly rate with a “total not to exceed” amount may be accepted. Work included in an emergency request for proposals shall be held to the minimum necessary to eliminate hazards and/or prevent further damage. Corrective work shall not be included in the emergency request, but shall be incorporated into a separate project for later solicitation. Projects for emergency repairs the cost of which exceeds twenty-five thousand dollars ($25,000) require approval of the director. Requests shall include scope, source of funding and, when appropriate, drawings, specifications and proposal forms.
(2) Contracts. Approval by the director of a contract(s) for a project in the program for twenty-five thousand dollars ($25,000) or more will be granted only after review and approval of drawings and specifications in accordance with 1 CSR 30-3.030. The bid tabulation and the contract shall be submitted together for review and approval.
(3) Project Supervision. The director, as representative for the owner, shall be responsible for supervision of work on all projects under this program.
(A) Department/Agency/Site. The department/agency and personnel at the project site are responsible for providing the contractor with reasonable access to the project site, available utility connections and authorized storage areas. These shall be arranged so as to minimize interference between necessary operations at the facility and the project work. Department/agency/site personnel shall:
and informal coordination with the contractor, but shall not assist the contractor with, or issue instructions on, project work; and
extent possible, the inspector of the work and the designer in observing the work, equipment and materials on the site. Unusual occurrences or apparent problems will be reported to the inspector at the earliest opportunity.
representative shall have responsibility for supervision and administration of the contract(s) on the project(s). This representative shall:
designer, official instructions to the contractor, provide coordination as necessary with site personnel and verify work or materials included in payment estimates;
ing the work and provide coordination between contractors working at the project site;
cated by conditions or special requirements, as well as for periodic reports or recommendations to the director;
gram manager/service level manager of scheduled visits, meetings and inspections; and
posals, request for information, contract changes, etc. having to do with the progress of the work.
(C) Designer. The designer, when construction administration is included in their responsibility, shall:
that the work is in accordance with the contract documents;
inspector, official instructions to the contractor and verify work or materials included in payment estimates;
the sequence and control for the several phases and trades involved in the project work;
response for all submissions from the contractor and/or along with clarifications or interpretations of the intent of the contract documents;
to review the work or progress or to resolve problems. Reports for periodic progress meetings shall include a resume of work to date, progress for the period, scheduled versus actual progress and efforts to resolve differences between the schedule and actual progress;
ing problems of unusual occurrences or unanticipated requirements; and
ducible, as-built drawings for the project.
(D) Contractor. The contractor shall be responsible for providing:
all times when work is in progress. This superintendent shall have the capability and authority to supervise the work and to make decisions relating to the work. Inspection and/or observation by others shall not be used as a substitute for the contractor’s superintendent;
tity of workmanship, materials and equipment on-site and/or incorporated in the project will meet the requirements of the contract documents;
nel and equipment involved in the work under the contract along with coordination, as appropriate, with other contractors or personnel on the site. Access to the work site and/or storage areas will be controlled carefully to minimize interference with other personnel or activities at the site;
connections for, as well as metering and use of, utilities available at the site;
drawings legibly marked to show any changes to, or deviation from, the original contract drawings, all approved shop drawings and operating instructions for all equipment installed under the contract; and
ance with Occupational Safety and Hazard Administration (OSHA) regulations must be maintained at all times.
(H) Inspections. The contractor is responsible for completion of all work in accordance with the contract documents. Periodic visits and observations by the inspector and designer are for assistance and shall not be used as a substitute for the contractor’s required responsibilities under the terms of the contract.
tractor has substantially completed the work, s/he shall notify the inspector requesting a pre-final inspection and provide a complete list of all items remaining to be completed. The inspector, with the designer and contractor, shall review this list, examine the work and note any exceptions or additional items to be corrected or completed. After review of the items to be corrected and completed and considering the time necessary to accomplish these, a time and date will be set for final inspection.
shall be an examination of the completed project, with particular emphasis on the items for correction and completion established in the pre-final inspection. Representatives of the department/agency, and when appropriate, the grantor or donor of support funding shall be invited to participate in the final inspection along with the inspector, the designer and contractor. Any items remaining for correction and comple tion shall be noted and the contractor shall be given a specific time to accomplish these items. Items of testing and adjustment which are incomplete due to seasonal requirements will be scheduled for completion in the appropriate season. Final acceptance may be made after completion of all items except for testing or adjusting seasonal equipment. Design and Construction
ty period the facility operator shall inform the contractor of all deficiencies encountered needing correction. If not corrected within a reasonable period of time, the inspector shall be notified.
equipment, materials and work are guaranteed or warranted for at least one (1) year after final acceptance. During the tenth or eleventh month following completion, the designer shall schedule a meeting at the project site with the contractor, a representative of the department/agency/site and a representative of the director. Performance of items under guaranty or warranty will be examined to assure that they are providing satisfactory service. Deficiencies shall be noted and the contractors shall be given a specific time for correction. Payment/performance bonds shall not be released until after the warranty inspection and correction of noted deficiencies. This warranty inspection shall not be construed to limit or relieve any responsibility of the contractor to provide call-back or other service or correction of deficiencies during the warranty period for the equipment, materials or work on the project.
(4) Exemptions. There are specific exemptions from requirements of this rule provided by the Missouri Constitution or by the Revised Statutes of Missouri.
AUTHORITY: sections 8.310 and 8.320, RSMo 2000 and subsections 6 and 7 of section 15, 1974 Reorganization Act.* Original rule filed July 9, 1981, effective Feb. 15, 1982. Emergency amendment filed June 14, 1985, effective July 1, 1985, expired Oct. 29, 1985. Amended: Filed June 14, 1985, effective Aug. 26, 1985. Amended: Filed Nov. 30, 1993, effective July 10, 1994. Rescinded and readopted: Filed Nov. 5, 2007, effective June 30, 2008.
*Original authority: 8.310, RSMo 1958, amended 1965, 1984, 1987, 1995 and 8.320, RSMo 1958, amended 1965.