Viewing an earlier, undated versionView current - (a) No person may construct an LWECS without a site permit issued by the Public Utilities Commission.
- (b) Any person seeking to construct an LWECS shall submit an application to the commission for a site permit in accordance with this chapter and any rules adopted by the commission. The permitted site need not be contiguous land.
- (c) The commission shall make a final decision on an application for a site permit for an LWECS within 180 days after acceptance of a complete application by the commission. The commission may extend this deadline for cause.
- (d) The commission may place conditions in a permit and may deny, modify, suspend, or revoke a permit.