Minn. Stat. § 216B.62
Subd. 1.
[Repealed, 1980 c 614 s 191]
Subd. 2. Assessing specific utility.
Whenever the commission or department, in a proceeding upon its own motion, on complaint, or upon an application to it, shall deem it necessary, in order to carry out the duties imposed under this chapter and section 216A.085 (1) to investigate the books, accounts, practices, and activities of, or make appraisals of the property of, any public utility, (2) to render any engineering or accounting services to any public utility, or
Subd. 3. Assessing all public utilities.
The department and commission shall quarterly, at least 30 days before the start of each quarter, estimate the total of their expenditures in the performance of their duties relating to (1) public utilities under section 216A.085, sections
216B.01 to 216B.67, other than amounts chargeable to public utilities under subdivision 2 or 6, and (2) alternative energy engineering activity under section 216C.261. The remainder, except the amount assessed against cooperatives and municipalities for alternative energy engineering activity under subdivision 5, shall be assessed by the commission and department to the several public utilities in proportion to their respective gross operating revenues from retail sales of gas or electric service within the state during the last calendar year. The assessment shall be paid into the state treasury within 30 days after the bill has been transmitted via mail, personal delivery, or electronic service to the several public utilities, which shall constitute notice of the assessment and demand of payment thereof. The total amount which may be assessed to the public utilities, under authority of this subdivision, shall not exceed one-sixth of one percent of the total gross operating revenues of the public utilities during the calendar year from retail sales of gas or electric service within the state. The assessment for the third quarter of each fiscal year shall be adjusted to compensate for the amount by which actual expenditures by the commission and department for the preceding fiscal year were more or less than the estimated expenditures previously assessed.
Subd. 4. Objections.
Within 30 days after the date of the transmittal of any bill as provided by subdivisions 2 and 3, the public utility against which the bill has been rendered may file with the commission objections setting out the grounds upon which it is claimed the bill is excessive, erroneous, unlawful or invalid. The commission shall within 60 days hold a hearing and issue an order in accordance with its findings. The order shall be appealable in the same manner as other final orders of the commission.
Subd. 5. Assessing cooperatives and municipals.
The commission and department may charge cooperative electric associations, generation and transmission cooperative electric associations, municipal power agencies, and municipal electric utilities their proportionate share of the expenses incurred in the review and disposition of resource plans, adjudication of service area disputes, proceedings under section 216B.1691, 216B.2425, or 216B.243, and the costs incurred in the adjudication of complaints over service standards, practices, and rates. Cooperative electric associations electing to become subject to rate regulation by the commission pursuant to section 216B.026, subdivision 4, are also subject to this section. Neither a cooperative electric association nor a municipal electric utility is liable for costs and expenses in a calendar year in excess of the limitation on costs that may be assessed against public utilities under
Subd. 2.
A cooperative electric association, generation and transmission cooperative electric association, municipal power agency, or municipal electric utility may object to and appeal bills of the commission and department as provided in subdivision 4. The department shall assess cooperatives and municipalities for the costs of alternative energy engineering activities under section 216C.261. Each cooperative and municipality shall be assessed in proportion that its gross operating revenues for the sale of gas and electric service within the state for the last calendar year bears to the total of those revenues for all public utilities, cooperatives, and municipalities.
Subd. 5a. Assessing transmission companies.
The commission and department may charge transmission companies their proportionate share of the expenses incurred in the review and disposition of proceedings under sections 216B.2425, 216B.243, 216B.48, 216B.50, and 216B.79. A transmission company is not liable for costs and expenses in a calendar year in excess of the limitation on costs that may be assessed against public utilities under subdivision 2. A transmission company may object to and appeal bills of the commission and department as provided in subdivision 4.
Subd. 6. Administrative hearing costs.
Any amounts billed to the commission or the department by the Office of Administrative Hearings for public utility contested case hearings shall be assessed by the commission or the department against the public utility. The assessment shall be paid into the state treasury within 30 days after a bill, which constitutes notice of the assessment and demand for payment of it, has been transmitted to the public utility. Money received shall be credited to a special account and is appropriated to the commission or the department for payment to the Office of Administrative Hearings.