Minn. Stat. § 216B.2424
Subd. 1. Farm-grown closed-loop biomass.
For the purposes of this section, "farm-grown closed-loop biomass" means biomass, as defined in section 216C.051, subdivision 7, that:
(3) is fired in a new or substantially retrofitted electric generating facility that is:
(ii) designed to use biomass to meet at least 75 percent of its fuel requirements.
The legislature finds that the negative environmental impacts within 400 miles of the facility resulting from transporting and combusting the biomass are offset in that region by the environmental benefits to air, soil, and water of the biomass production.
Among the biomass fuel sources that meet the requirements of clause (2) are poplar, aspen, willow, switch grass, sorghum, alfalfa, and cultivated prairie grass.
Subd. 2. Interim exemption.
Subd. 3. Fuel exemption.
Over the duration of the contract of a biomass power facility selected to satisfy the mandate in subdivision 5, fuel sources that are not biomass may be used to satisfy up to 25 percent of the fuel requirements of a biomass power facility selected to satisfy the biomass power mandate in subdivision 5.
Subd. 4. Financial viability.
A biomass project developer must demonstrate to the public utility evidence of sufficient financial viability necessary for the construction and operation of the biomass project.
Subd. 5. Mandate.
A public utility, as defined in section 216B.02, subdivision 4, that operates a nuclear-powered electric generating plant within this state must construct and operate, purchase, or contract to construct and operate (1) by December 31, 1998, 50 megawatts of electric energy installed capacity generated by farm-grown closed-loop biomass scheduled to be operational by December 31, 2001; and (2) by December 31, 1998, an additional 75 megawatts of installed capacity so generated scheduled to be operational by December 31, 2002. Of the total 125 megawatts of biomass electric energy installed capacity required under this section, no more than 75 megawatts may be provided by a single project. Of the 75 megawatts of biomass electric energy installed capacity required under clause (2), no more than 25 megawatts of this capacity may be provided by a St. Paul district heating and cooling system cogeneration facility utilizing waste wood as a primary fuel source. The St. Paul district heating and cooling system cogeneration facility need not use biomass that complies with the definition in subdivision 1. The public utility must accept and consider on an equal basis with other proposals a proposal to satisfy the requirements of this section that includes a project that exceeds the megawatt capacity requirements of either clause (1) or (2) and that proposes to sell the excess capacity to the public utility or to other purchasers.