Minn. Stat. § 216B.1691
Subd. 1. Definitions.
Subd. 2. Eligible energy objectives.
Each electric utility shall make a good faith effort to generate or procure sufficient electricity generated by an eligible energy technology to provide its retail consumers, or the retail customers of a distribution utility to which the electric utility provides wholesale electric service, so that commencing in 2005, at least one percent of the electric utility's total retail electric sales to retail customers in Minnesota is generated by eligible energy technologies and seven percent of the electric utility's total retail electric sales to retail customers in Minnesota by 2010 is generated by eligible energy technologies.
Subd. 2a. Eligible energy technology standard.
(a) Except as provided in paragraph (b), each electric utility shall generate or procure sufficient electricity generated by an eligible energy technology to provide its retail customers in Minnesota, or the retail customers of a distribution utility to which the electric utility provides wholesale electric service, so that at least the following standard percentages of the electric utility's total retail electric sales to retail customers in Minnesota are generated by eligible energy technologies by the end of the year indicated:
| (1) | 2012 | 12 percent |
| (2) | 2016 | 17 percent |
| (3) | 2020 | 20 percent |
| (4) | 2025 | 25 percent. |
(b) An electric utility that owned a nuclear generating facility as of January 1, 2007, must meet the requirements of this paragraph rather than paragraph (a). An electric utility subject to this paragraph must generate or procure sufficient electricity generated by an eligible energy technology to provide its retail customers in Minnesota or the retail customer of a distribution utility to which the electric utility provides wholesale electric service so that at least the following percentages of the electric utility's total retail electric sales to retail customers in Minnesota are generated by eligible energy technologies by the end of the year indicated:
| (1) | 2010 | 15 percent |
| (2) | 2012 | 18 percent |
| (3) | 2016 | 25 percent |
| (4) | 2020 | 30 percent. |
Of the 30 percent in 2020, at least 25 percent must be generated by solar energy or wind energy conversion systems and the remaining five percent by other eligible energy technology. Of the 25 percent that must be generated by wind or solar, no more than one percent may be solar generated and the remaining 24 percent or greater must be wind generated.
Subd. 2b. Modification or delay of standard.
(a) The commission shall modify or delay the implementation of a standard obligation, in whole or in part, if the commission determines it is in the public interest to do so. The commission, when requested to modify or delay implementation of a standard, must consider:
(7) other statutory obligations imposed on the commission or a utility.
The commission may modify or delay implementation of a standard obligation under clauses (1) to (3) only if it finds implementation would cause significant rate impact, requires significant measures to address reliability, or raises significant technical issues. The commission may modify or delay implementation of a standard obligation under clauses (4) to (6) only if it finds that the circumstances described in those clauses were due to circumstances beyond an electric utility's control and make compliance not feasible.
Subd. 2c. Use of integrated resource planning process.
The commission may exercise its authority under subdivision 2b to modify or delay implementation of a standard obligation as part of an integrated resource planning proceeding under section 216B.2422. The commission's authority must be exercised according to subdivision 2b. The order to delay or modify shall not be considered advisory with respect to any electric utility. This subdivision is in addition to and does not limit the commission's authority to modify or delay implementation of a standard obligation in other proceedings before the commission.
Subd. 2d. Commission order.
The commission shall issue necessary orders detailing the criteria and standards by which it will measure an electric utility's efforts to meet the renewable energy objectives of subdivision 2 to determine whether the utility is making the required good faith effort. In this order, the commission shall include criteria and standards that protect against undesirable impacts on the reliability of the utility's system and economic impacts on the utility's ratepayers and that consider technical feasibility.
Subd. 3. Utility plans filed with commission.
(a) Each electric utility shall report on its plans, activities, and progress with regard to the objectives and standards of this section in its filings under section 216B.2422 or in a separate report submitted to the commission every two years, whichever is more frequent, demonstrating to the commission the utility's effort to comply with this section. In its resource plan or a separate report, each electric utility shall provide a description of:
Subd. 4. Renewable energy credits.
Subd. 5. Technology based on fuel combustion.
(a) Electricity produced by fuel combustion through fuel blending or co-firing under paragraph (b) may only count toward a utility's objectives or standards if the generation facility:
Subd. 6.
[Repealed by amendment, 2007 c 3 s 1]
Subd. 7. Compliance.
The commission must regularly investigate whether an electric utility is in compliance with its good faith objective under subdivision 2 and standard obligation under subdivision 2a. If the commission finds noncompliance, it may order the electric utility to construct facilities, purchase energy generated by eligible energy technology, purchase renewable energy credits, or engage in other activities to achieve compliance. If an electric utility fails to comply with an order under this subdivision, the commission may impose a financial penalty on the electric utility in an amount not to exceed the estimated cost of the electric utility to achieve compliance. The penalty may not exceed the lesser of the cost of constructing facilities or purchasing credits. The commission must deposit financial penalties imposed under this subdivision in the energy and conservation account established in the special revenue fund under section 216B.241, subdivision 2a. This subdivision is in addition to and does not limit any other authority of the commission to enforce this section.
Subd. 8. Relation to other law.
This section does not limit the authority of the commission under any other law, including, without limitation, sections 216B.2422 and 216B.243.
Subd. 9. Local benefits.
The commission shall take all reasonable actions within its statutory authority to ensure this section is implemented to maximize benefits to Minnesota citizens, balancing factors such as local ownership of or participation in energy production, development and ownership of eligible energy technology facilities by independent power producers, Minnesota utility ownership of eligible energy technology facilities, the costs of energy generation to satisfy the renewable standard, and the reliability of electric service to Minnesotans.
Subd. 10. Utility acquisition of resources.
A competitive resource acquisition process established by the commission prior to June 1, 2007, shall not apply to a utility for the construction, ownership, and operation of generation facilities used to satisfy the requirements of this section unless, upon a finding that it is in the public interest, the commission issues an order on or after June 1, 2007, that requires compliance by a utility with a competitive resource acquisition process. A utility that owns a nuclear generation facility and intends to construct, own, or operate facilities under this section shall file with the commission on or before March 1, 2008, a renewable energy plan setting forth the manner in which the utility proposes to meet the requirements of this section, including a proposed schedule for purchasing renewable energy from C-BED and non-C-BED projects. The utility shall update the plan as necessary in its filing under section 216B.2422. The commission shall approve the plan unless it determines, after public hearing and comment, that the plan is not in the public interest. As part of its determination of public interest, the commission shall consider the plan's allocation of projects among C-BED, non-C-BED, and utility-owned projects, balancing the state's interest in: