Minn. Stat. § 216B.1621
Subd. 1. Agreement.
When a retail customer of a public utility proposes to acquire power from or construct a new electric power generation facility in the assigned service area of the utility serving the retail customer to provide all or part of the customer's electric service needs, the public utility may negotiate with and enter into an agreement with the customer to supply electric power to the customer in order to defer construction of the facility until the utility has need of power generated by the proposed facility, if the Public Utilities Commission approves the agreement under subdivision 2.
Subd. 2. Commission approval.
(a) The commission shall approve an agreement under this section upon finding that: