Subd. 1. Purpose.
The purpose of this section is to:
Subd. 2. Distributed generation; generic proceeding.
(a) The commission shall initiate a proceeding within 30 days of July 1, 2001, to establish, by order, generic standards for utility tariffs for the interconnection and parallel operation of distributed generation fueled by natural gas or a renewable fuel, or another similarly clean fuel or combination of fuels of no more than ten megawatts of interconnected capacity. At a minimum, these tariff standards must:
Subd. 3. Distributed generation tariff.
Within 90 days of the issuance of an order under subdivision 2:
Subd. 3a. Project information.
(a) Beginning July 1, 2014, each electric utility shall request an applicant for interconnection of distributed renewable energy generation to provide the following information, in a format prescribed by the commissioner:
Subd. 4. Reporting requirements.