(b) At a minimum, the report must include, for each guideway project:
- (1) a brief description of the project, including projected ridership;
- (2) a summary of the overall status and current phase of the project;
- (3) a timeline that includes (i) project phases or milestones; (ii) expected and known dates of commencement of each phase or milestone; and (iii) expected and known dates of completion of each phase or milestone;
- (4) a brief progress update on specific project phases or milestones completed since the last previous submission of a report under this subdivision; and
(5) a summary financial plan that identifies, to the extent available:
- (i) capital expenditures, including expenditures to date and total projected expenditures, with a breakdown by committed and proposed sources of funds for the project; and
- (ii) estimated annual operations and maintenance expenditures reflecting the level of detail available in the current phase of the project development, with a breakdown by committed and proposed sources of funds for the projects in the Metropolitan Council's transportation policy plan.