Minn. Stat. § 161.3209
Subd. 1. Solicitation of proposals.
If the commissioner determines that a construction manager/general contractor method of procurement is appropriate for a project, the commissioner shall establish a two-phase procedure for awarding the construction manager/general contractor contract, as described in subdivisions 2 and 3.
Subd. 2. Phase 1 - request for proposals.
(a) The commissioner shall prepare or have prepared an RFP for each construction manager/general contractor contract as provided in this section. The RFP must contain, at a minimum, the following elements:
(b) Before receiving any responses to the RFP:
(2) the technical review committee shall evaluate the construction manager/general contractor proposals according to criteria and subcriteria published in the RFP and procedures established by the commissioner. The commissioner shall, as designated in the RFP, evaluate construction manager/general contractor proposals on the basis of best value as defined in section 16C.05, or using the qualifications-based selection process set forth in section 16C.095, except that subdivision 1 of section 16C.095 shall not apply. If the commissioner does not receive at least two proposals from construction managers, the commissioner may:
Subd. 3. Phase 2 - construction manager/general contractor contract.
(a) Before conducting any construction-related services, the commissioner shall: