Subd. 1. Claims on performance bonds.
In the event of a claim by the public body on a performance bond, no action shall be maintained later than permitted under the statute of limitations applicable to the claim. Nothing in this subdivision may be construed to otherwise affect the common law or equitable rights of performance bond sureties, principals, or public bodies that are obligees.
Subd. 2. Claims on payment bonds.
(a) In the event of a claim on a payment bond by a person furnishing labor and materials, no action shall be maintained on the payment bond unless, within 120 days after completion, delivery, or provision by the person of its last item of labor and materials, for the public work, the person serves written notice of claim under the payment bond personally or by certified mail upon the surety that issued the bond and the contractor on whose behalf the bond was issued at their addresses as stated in the bond specifying the nature and amount of the claim and the date the claimant furnished its last item of labor and materials for the public work. The addresses of the contractor and the surety listed on the bond must be addresses at which the companies are authorized to accept service of the notice of the claim. If an agent or attorney-in-fact is authorized to accept service of notice of the claim for the contractor or surety, that fact must be expressly stated in the bond along with the address of the agent or attorney-in-fact at which service of the notice of the claim can be made. For the purpose of this section, notice is sufficient if served personally or via certified mail to the addresses of the contractor and surety listed on the bond. The form of notice is sufficient if it is substantially as follows:
NOTICE OF CLAIM ON PAYMENT BOND FOR PUBLIC WORK
| TO: . | |||
| (Surety that issued payment bond) | |||
| and . | |||
| (The contractor on whose behalf the bond was issued) | |||
| NOTICE IS HEREBY GIVEN that the undersigned claimant | |||
| has a claim against the above-named surety for labor and materials | |||
| furnished by the undersigned for the public work described | |||
| as follows: . | |||
| . | |||
| (Description of the public work) | |||
| The labor and materials were furnished under a contract | |||
| or agreement with | |||
| . | |||
| (Name and address of contractor or supplier requesting labor and materials from the claimant) | |||
| The nature of the labor and materials furnished is as follows: | |||
| . | |||
| The amount of the claim is: . | |||
| The date the claimant last furnished labor and materials to this public work is the ...... day of ......................., ............ | |||
| Claimant seeks payment of the claim according to the law. |
| . | ||||
| Claimant | ||||
| . | ||||
| Address | ||||
| . | ||||
| STATE OF . | ||||
| ss. | ||||
| COUNTY OF . | ||||
| ......................... being duly sworn on oath says that ....... | ||||
| is ......................... of the claimant named above and has | ||||
| knowledge of the claim and that the claim is correct, and no | ||||
| part of the claim has been paid. | ||||
| . | ||||
| Signed and sworn to before me | ||||
| on . | , | |||
| by . | (Notary Seal) | |||
| . | ||||
| Notary Public |