Minn. Stat. § 116C.575
Subd. 1. Alternative review.
An applicant who seeks a site permit or route permit for one of the projects identified in this section shall have the option of following the procedures in this section rather than the procedures in section 116C.57. The applicant shall notify the chair at the time the application is submitted which procedure the applicant chooses to follow.
Subd. 2. Applicable projects.
The requirements and procedures in this section apply to the following projects:
Subd. 3. Application.
The applicant for a site or route permit for any of the projects listed in subdivision 2 who chooses to follow these procedures shall submit information as the board may require, but the applicant shall not be required to propose a second site or route for the project. The applicant shall identify in the application any other sites or routes that were rejected by the applicant and the board may identify additional sites or routes to consider during the processing of the application. The chair of the board shall determine whether an application is complete and advise the applicant of any deficiencies.
Subd. 4. Notice of application.
Upon submission of an application under this section, the applicant shall provide the same notice as required by section 116C.57, subdivision 2b.
Subd. 5. Environmental review.
For the projects identified in subdivision 2 and following these procedures, the board shall prepare an environmental assessment. The environmental assessment shall contain information on the human and environmental impacts of the proposed project and other sites or routes identified by the board and shall address mitigating measures for all of the sites or routes considered. The environmental assessment shall be the only state environmental review document required to be prepared on the project.
Subd. 6. Public hearing.
The board shall hold a public hearing in the area where the facility is proposed to be located. The board shall give notice of the public hearing in the same manner as notice under section 116C.57, subdivision 2d. The board shall conduct the public hearing under procedures established by the board. The applicant shall be present at the hearing to present evidence and to answer questions. The board shall provide opportunity at the public hearing for any person to present comments and to ask questions of the applicant and board staff. The board shall also afford interested persons an opportunity to submit written comments into the record.
Subd. 7. Timing.
The board shall make a final decision on an application within 60 days after completion of the public hearing. A final decision on the request for a site permit or route permit under this section shall be made within six months after the chair's determination that an application is complete. The board may extend this time limit for up to three months for just cause or upon agreement of the applicant.
Subd. 8. Considerations.
The considerations in section 116C.57, subdivision 4, shall apply to any projects subject to this section.
Subd. 9. Final decision.