Minn. Stat. § 126C.69
Subd. 1. Capital grant and loan requests and uses.
Capital grants and loans are available only to qualifying districts. Capital grants and loans must not be used for the construction of swimming pools, ice arenas, athletic facilities, auditoriums, bus garages, or heating system improvements. Proceeds of the grants and loans may be used only for sites for education facilities and for acquiring, bettering, furnishing, or equipping education facilities. Contracts must be entered into within 18 months after the date on which each grant and loan is approved. For purposes of this section, "education facilities" includes space for Head Start programs and social service programs.
Subd. 2. Capital grant and loan eligibility.
Beginning July 1, 2020, a district is not eligible for a capital grant and loan unless the district's estimated net debt tax rate as computed by the commissioner after debt service equalization aid would be more than 41.98 percent of adjusted net tax capacity. The estimate must assume a 20-year maturity schedule for new debt.
Subd. 3. District request for review and comment.
A district or a joint powers district that intends to apply for a capital grant and loan must submit a proposal to the commissioner for review and comment according to section 123B.71 by July 1 of an odd-numbered year. The commissioner shall prepare a review and comment on the proposed facility, regardless of the amount of the capital expenditure required to construct the facility. In addition to the information provided under section 123B.71, subdivision 9, the commissioner shall require that predesign packages comparable to those required under section 16B.335 be prepared by the applicant school district. The predesign packages must be sufficient to define the scope, cost, and schedule of the project and must demonstrate that the project has been analyzed according to appropriate space needs standards and also consider the following criteria in determining whether to make a positive review and comment.
(a) To grant a positive review and comment the commissioner shall determine that all of the following conditions are met:
(b) The commissioner may grant a negative review and comment if:
Subd. 4. Multiple district proposals; review and comment.
In addition to the requirements of subdivision 3, the commissioner may use additional requirements to determine a positive review and comment on projects that are designed to serve more than one district. These requirements may include:
Subd. 5. Adjacent district comments.
The district must present the proposed project to the board of each adjacent district at a public meeting of that district. The board of an adjacent district must make a written evaluation of how the project will affect the future education and building needs of the adjacent district. The board must submit the evaluation to the applying district within 30 days of the meeting.
Subd. 6. District application for capital grant and loan.
The school board of a district desiring a capital grant and loan shall adopt a resolution stating the amount proposed to be funded, the purpose for which the funding is requested, and an estimate of the dates when the facilities for which the funding is requested will be contracted for and completed. Applications for grants and loans must be accompanied by a copy of the adopted board resolution and copies of the adjacent district evaluations. The commissioner shall retain the evaluation as part of a permanent record of the district submitting the evaluation.
Applications must be in the form and accompanied by the additional data required by the commissioner. Applications must be received by the commissioner by September 1 of an odd-numbered year. A district must resubmit an application each odd-numbered year. Capital grant and loan applications that do not receive voter approval or are not approved in law cancel July 1 of the year following application. When an application is received, the commissioner shall obtain from the commissioner of revenue the information in the Revenue Department's official records that is required to be used in computing the debt limit of the district under section 475.53, subdivision 4.
Subd. 7. Commissioner review; district proposals.
By November 1 of each odd-numbered year, the commissioner must review all applications for capital grants and loans that have received a positive review and comment. When reviewing applications, the commissioner must consider whether the criteria in subdivision 3 have been met. The commissioner may not approve an application if all of the required deadlines have not been met. The commissioner may either approve or reject an application for a capital grant and loan.
Subd. 8. Commissioner recommendations.
The commissioner shall examine and consider applications for capital grants and loans that have been approved and promptly notify any district rejected of the decision.
The commissioner shall report each capital grant and loan that has been approved by the commissioner and that has received voter approval to the education committees of the legislature by January 1 of each even-numbered year. The commissioner must not report a capital grant and loan that has not received voter approval. The commissioner shall also report on the money remaining in the capital loan account and, if necessary, request that another bond issue be authorized.
Subd. 9. Grant and loan amount limits.
(a) A grant and loan must not be recommended for approval for a district exceeding an amount computed as follows:
(c) The loan amount equals the lesser of the total grant and loan approved or:
Subd. 10. Legislative action.
Each capital grant and loan must be approved in a law.
If the aggregate amount of the capital grants and loans exceeds the amount that is or can be made available, the commissioner shall allot the available amount among any number of qualified applicant districts, according to the commissioner's judgment and discretion, based upon the districts' respective needs.
Subd. 11. District referendum.
After receipt of the review and comment on the project and before January 1 of the even-numbered year, the question authorizing the borrowing of money for the facilities must be submitted by the school board to the voters of the district at a regular or special election. The question submitted must state the total amount to be borrowed from all sources. Approval of a majority of those voting on the question is sufficient to authorize the issuance of the obligations on public sale in accordance with chapter 475. The face of the ballot must include the following statement: "APPROVAL OF THIS QUESTION DOES NOT GUARANTEE THAT THE SCHOOL DISTRICT WILL RECEIVE A CAPITAL GRANT AND LOAN FROM THE STATE. THE GRANT AND LOAN MUST BE APPROVED BY THE STATE LEGISLATURE AND IS DEPENDENT ON AVAILABLE FUNDING." The district must mail to the commissioner a certificate by the clerk showing the vote at the election.
Subd. 12. Contract.
Subd. 13. Loan forgiveness.
If any capital loan is not paid within 50 years after it is granted from maximum effort debt service levies in excess of required debt service levies, the liability of the district on the loan is satisfied and discharged and interest on the loan ceases.
Subd. 14. Participation by county auditor; record of contract; payment of loan.
The district must file a copy of the capital loan contract with the county auditor of each county in which any part of the district is situated. The county auditor shall enter the capital loan, evidenced by the contract, in the auditor's bond register. The commissioner shall keep a record of each capital grant and loan contract showing the name and address of the district, the date of the contract, and the amount of the grant and loan initially approved. On receipt of the resolution required in subdivision 12 and documentation of expenditures under the contract, the commissioner shall issue payments on the capital grant and loan account for the amount that may be disbursed under subdivision 1.
Subd. 15. Bond sale limitations.