Minn. Stat. § 16C.33
Subd. 1. Conflict of interest.
A board member may not participate in the review, discussion, or selection of a primary designer, a design-builder, or a firm in which the member has a financial interest.
Subd. 2. Design-builder licensing requirements.
Subd. 3. Solicitation of qualifications or proposals.
(b) A request for qualifications or proposals soliciting design-builders shall be prepared for each design-build contract pursuant to subdivision 5 or 7. The request for qualifications or proposals shall contain, at a minimum, the following elements:
Subd. 4. University of Minnesota projects.
Subd. 5. Design-build qualifications-based selection process.
(a) In a design-build qualifications-based selection process, the following shall apply:
(b)(1) the commissioner shall establish procedures for determining the appropriate content of each request for qualifications, the weighted criteria and subcriteria to be used to evaluate the design-builders, and the procedures for evaluating qualifications in an open, competitive, and objective manner; (2) the criteria and subcriteria shall include, but are not limited to, the proposer's experience as a constructor or primary designer, including capacity of key personnel, technical competence and capability to perform, the past performance of the proposer and its employees, its safety record and compliance with state and federal law, and availability to and familiarity with the project locale; (3) the commissioner may include in the request for qualifications criteria a requirement that the proposer include the overhead and fee that the design-builder proposes to charge for its construction services; and (4) the commissioner shall issue a request for qualifications that includes the information as described in subdivision 3.
(c) After obtaining and evaluating qualifications from each design-builder, in accordance with the weighted criteria and subcriteria and procedures set forth in the request for qualifications, the board shall select a short list of at least three and no more than five proposals. The board must receive at least three proposals from design-builders or the commissioner shall either:
Subd. 6. Design-build qualifications-based acceptance by commissioner.
Subd. 7. Design-build design and price-based proposals.
(a) In a design and price-based selection process the following shall apply:
(b) After obtaining and evaluating qualifications from each design-builder, in accordance with the weighted criteria and subcriteria and procedures set forth in the request for qualifications, the board shall select a short list of three proposers. The board must receive at least three proposals from design-builders or the commissioner shall either:
(c) The commissioner shall issue a request for proposals to the selected design-builders. The submitted proposals shall consist of, at a minimum, the following elements:
Subd. 8. Design-build design and price-based selection process.