- (a) A supplier may notify a lender of a lien by delivering a lien-notification statement to the lender in an envelope marked "IMPORTANT-LEGAL NOTICE," addressed to the lender. Delivery of the statement shall be by certified mail or another method evidencing date of receipt.
(b) The lien-notification statement must be in a form approved by the secretary of state, be signed by the purchaser, and state the following:
- (1) The name and business address of the lender;
- (2) the name and address of the supplier claiming the lien;
- (3) the date or anticipated date or dates of furnishing agricultural production input, a description of the input, and the retail cost, or anticipated retail costs of the agricultural production input;
- (4) the name and residential address of the person to whom the agricultural production input was or is to be furnished;
- (5) for crop production input, the name and residential address of the owner of the crops and a description of the real estate where the crops to which the lien attaches are growing or are to be grown and for livestock production input, a description of the livestock and the location where the livestock will be or are being raised or fed; and
- (6) a statement that the products and proceeds of the crops or livestock are covered by the lien.
(c) Within five business days after receiving a lien-notification statement, the lender must, by certified mail, furnish the supplier with either:
- (1) A letter of commitment to advance part or all of the retail cost stated in the lien-notification statement; or
- (2) a written refusal to furnish such a letter of commitment.
- (d) If the lender furnishes a letter of commitment to advance part or all of the retail cost stated in the lien-notification statement, or a written refusal to furnish such a letter of commitment, the lien of the supplier shall not have priority over a previously perfected security interest of the lender.
- (e) If the lender does not send the supplier a letter of commitment or a written refusal to furnish a letter of commitment within five business days after receiving the lien-notification statement, the lien for the unpaid retail cost of the agricultural production input stated in the lien-notification statement shall have priority over a perfected security interest of the lender in collateral subject to the lien and proceeds thereof.
- (f) Subject to the limitation of subsection (d) liens established under this act have priority over any and all other liens, except those created under K.S.A. 58-207 and 58-220, on the crops or livestock for which input is furnished.
- (g) An agricultural production lien statement shall be used only in the manner described in this section and shall not otherwise be used as a substitute for a financing statement filed under part 4 of article 9 of the uniform commercial code.
L. 1985, ch. 4, § 2; September 1.