Sec. 114. (a) A remining operation on a site that contains a preexisting highwall must comply with section 112 of this rule, except as provided under this section.
(b) Section 112(a)(2) of this rule does not apply to a remining operation if the volume of reasonably available spoil is demonstrated, in writing, to the director to be insufficient to completely backfill the reaffected or enlarged highwall. The highwall must be eliminated to the extent technically practicable as follows:
(Natural Resources Commission; 312 IAC 25-6-114; filed Jun 21, 2001, 2:53 p.m.: 24 IR 3570, eff Dec 1, 2001; readopted filed May 29, 2007, 9:51 a.m.: 20070613-IR-312070146RFA; readopted filed Sep 19, 2013, 10:12 a.m.: 20131016-IR-312130125RFA; errata filed Jan 31, 2019, 1:45 p.m.: 20190213-IR-312190079ACA; readopted filed Mar 26, 2019, 3:40 p.m.: 20190424-IR-312190011RFA; readopted filed Mar 25, 2025, 9:50 a.m.: 20250423-IR-312240574RFA)