Ind. Admin. Code tit. 312, r. 25-6-112
Authority: IC 14-34-2-1
Affected: IC 14-34
Sec. 112. (a) Disturbed areas shall be backfilled and graded to include the following:
(b) Spoil, except excess spoil disposed under subsection (d) or section 98 of this rule, shall be returned to the mined-out surface area.
(c) Spoil and waste materials shall be compacted where advisable to ensure stability or to prevent leaching of toxic materials.
(d) Spoil may be placed on the bonded, permitted area outside the mined-out surface area in nonsteep slope areas to restore the approximate original contour by blending the spoil into the surrounding terrain if the following requirements are met:
(e) Disposal of coal processing waste and underground development waste in the mined-out surface area shall be under sections 99 and 101 of this rule, except that a long term static safety factor of one and three-tenths (1.3) shall be achieved.
(f) Exposed coal seams, acid-and toxic-forming materials, and combustible materials exposed, used, or produced during mining shall be adequately covered with nontoxic and noncombustible earthen material, or treated, to control the impact on surface and ground water under section 76 of this rule to prevent sustained combustion and to minimize adverse effects on plant growth and the approved postmining land use.
(g) The director may approve as a term of a permit the construction of cut-and-fill terraces if the permittee demonstrates:
(h) Small depressions (which do not interfere with the approved postmining land use) may be constructed if needed to retain moisture, minimize erosion, create and enhance wildlife habitat, or assist revegetation.
(i) Permanent impoundments may remain if authorized by the director under section 84 of this rule.
(j) Preparation of final-graded surfaces shall be conducted to minimize erosion and to provide a surface for replacement of topsoil that will minimize slippage.
(k) The postmining slope may vary from the approximate original contour if:
(l) If sufficient spoil is not otherwise available to comply with this section, the director may approve as a term of a permit a modification of the requirements of this section under section 144(e) of this rule for underground mining operations that affect previously mined lands that:
(Natural Resources Commission; 312 IAC 25-6-112; filed Jun 21, 2001, 2:53 p.m.: 24 IR 3569, eff Dec 1, 2001; readopted filed May 29, 2007, 9:51 a.m.: 20070613-IR-312070146RFA; readopted filed Sep 19, 2013, 10:12 a.m.: 20131016-IR-312130125RFA; readopted filed Mar 26, 2019, 3:40 p.m.: 20190424-IR-312190011RFA; readopted filed Mar 25, 2025, 9:50 a.m.: 20250423-IR-312240574RFA)