Ind. Admin. Code tit. 312, r. 22-4-1
Authority: IC 14-10-2-4; IC 14-21-1-31
Affected: IC 14-21-1
Sec. 1. (a) This rule provides an expedited licensure process for cemetery restoration.
(b) A person who qualifies for and complies with this rule is not required to obtain approval of a plan under 312 IAC 21-3-3 or a permit under 312 IAC 22-2-3.
(c) A license is not available under this rule for either of the following:
(Natural Resources Commission; 312 IAC 22-4-1; filed Jan 5, 2011, 3:12 p.m.: 20110202-IR-312100059FRA; readopted filed Sep 19, 2013, 10:16 a.m.: 20131016-IR-312130184RFA; readopted filed Mar 26, 2019, 3:39 p.m.: 20190424-IR-312190004RFA; readopted filed Mar 25, 2025, 9:50 a.m.: 20250423-IR-312240574RFA)