Ind. Admin. Code tit. 312, r. 10.5-3-2
Authority: IC 14-27-7.5-8
Affected: IC 14-27-7.5
Sec. 2. (a) This section establishes a process by which a dam owner or another affected person may request reconsideration of a determination of hazard classification made under section 1 of this rule.
(b) The dam owner or other affected person may submit any technical information or reports that were not previously available to the division.
(c) The dam owner's or other affected person's professional engineer may develop and submit a maximum breach inundation area and current damage evaluation assessing the downstream area affected by a dam breach.
(1) If the maximum breach inundation area and current damage evaluation predicts any of the following, the dam shall be classified as high hazard:
(C) Interruption of service for more than one (1) day on any of the following:
(2) If the maximum breach inundation area and current damage evaluation predicts any of the following, the dam shall be classified as significant hazard:
(A) Interruption of service for not more than one (1) day on any of the following:
(D) Damage to important utilities where service would be interrupted for not more than one (1) day, but either of the following may occur:
(Natural Resources Commission; 312 IAC 10.5-3-2; filed Jan 26, 2007, 10:45 a.m.: 20070221-IR-312060092FRA; readopted filed Sep 19, 2013, 10:13 a.m.: 20131016-IR-312130162RFA; readopted filed Jul 18, 2019, 8:57 a.m.: 20190814-IR- 312190291RFA; readopted filed Mar 25, 2025, 9:50 a.m.: 20250423-IR-312240574RFA)