Ind. Admin. Code tit. 312, r. 10-3-4
Authority: IC 14-28-1-5
Affected: IC 4-21.5-3-8; IC 5-3-1-6; IC 14-11-4; IC 14-28-1-28
Sec. 4. (a) This section establishes the criteria and procedures for seeking authorization for a commission floodway under IC 14-28-1-28.
(b) A commission floodway is an alternative to the processes used to designate a floodway under section 2 or 3 of this rule.
(c) A person seeking to use this section shall make an application for approval of a commission floodway on a departmental form delivered to the division. Before being deemed complete, the application shall establish the following:
(1) The boundary of the commission floodway must not exclude an area that would otherwise be designated as a floodway under IC 14-28-1 and this rule unless each of the following is satisfied:
(A) With respect to any fill or structures within the excluded area, one (1) of the following must be demonstrated:
(C) "As built" plans certified by a registered professional engineer demonstrate both of the following:
(5) Construction resulting from development of the commission floodway will not do any of the following:
(7) Notice of the proposed commission floodway published at least two (2) times, seven (7) days apart, as follows:
(d) After the department has completed its review and analysis of the application, the deputy director for the bureau of water and resource regulation shall issue an order granting, denying, or conditioning the authorization for a commission floodway. The department may require as a condition of the order that an easement or similar encumbrance be placed in the record of title for the area covered by the commission floodway to ensure compliance with its terms, including conditions that must be met before an abode may be placed on the site pursuant to subsection (c)(4). Copies of the order, together with a statement of how administrative review of the order may be sought from the commission, shall be served upon the following:
(e) The authorization of a commission floodway shall be effective upon the latest of the following occurrences:
(1) If no request for administrative review is filed in a timely fashion, the latter of the following:
(Natural Resources Commission; 312 IAC 10-3-4; filed Jul 5, 2001, 9:12 a.m.: 24 IR 3390, eff Jan 1, 2002; readopted filed Jul 21, 2008, 12:00 p.m.: 20080813-IR-312080072RFA; readopted filed Sep 22, 2014, 12:34 p.m.: 20141022-IR-312140065RFA; readopted filed Sep 16, 2020, 8:17 a.m.: 20201014-IR-312200345RFA; errata filed Mar 18, 2026, 9:59 a.m.: 20260325-IR-312260094ACA)