Ind. Admin. Code tit. 105, r. 13-3-6
Authority: IC 8-23-2-5; IC 8-23-2-6
Affected: IC 8-1-26
Sec. 6. (a) The utility, contractor, and department shall perform the duties imposed by the approved work plan, contract, and this article within the time frames specified.
(b) Factors that shall excuse a utility from meeting the schedule in its approved work plan include the following:
(1) The facility relocation was impacted by any of the following:
(4) If a facility is discovered during the process required by IC 8-1-26, has not been previously identified as being within the improvement project limits, and the utility can show the following:
(c) If an approved work plan requires adjustment due to the occurrence of one (1) or more factors enumerated in subsection (b), the department and the utility shall proceed as directed in section 5(b) of this rule.
(Indiana Department of Transportation; 105 IAC 13-3-6; filed Apr 14, 2008, 10:23 a.m.: 20080514-IR-105070494FRA; readopted filed Oct 2, 2013, 11:39 a.m.: 20131030-IR-105130295RFA; readopted filed Oct 4, 2019, 9:49 a.m.: 20191030-IR-105190422RFA; readopted filed Oct 21, 2025, 3:46 p.m.: 20251112-IR-105240645RFA)