Ind. Admin. Code tit. 105, r. 13-1-2
Authority: IC 8-23-2-5; IC 8-23-2-6
Affected: IC 8-23-2
Sec. 2. (a) This article applies to improvement projects, as defined in 105 IAC 13-2-10, when the:
(2) design survey was completed before June 20, 2008, if the affected utility was provided:
(b) The department may require a utility to comply with a reasonable shortened process or expedited schedule when an emergency exists that could affect:
(c) When this article requires information, documents, or other notices to be delivered or provided to the department, it shall mean to the chief engineer or the chief engineer's designee unless the department has directed the utility in writing to a specific representative or office.
(Indiana Department of Transportation; 105 IAC 13-1-2; filed Apr 14, 2008, 10:23 a.m.: 20080514-IR- 105070494FRA; readopted filed Oct 2, 2013, 11:39 a.m.: 20131030-IR-105130295RFA; readopted filed Oct 4, 2019, 9:49 a.m.: 20191030-IR-105190422RFA; readopted filed Oct 21, 2025, 3:46 p.m.: 20251112-IR-105240645RFA)