Ind. Code § 8-1-8.4-6
(a) Except as provided in subsection (c), or unless an energy utility has elected to file for:
(2) the recovery of costs;
under another statute, an energy utility that seeks to recover federally mandated costs under section 7(c) of this chapter must obtain from the commission a certificate that states that public convenience and necessity is served by the energy utility's compliance project.
(b) The commission shall issue a certificate of public convenience and necessity under section 7(b) of this chapter if the commission finds that the compliance project allows the energy utility to comply directly or indirectly with one (1) or more federally mandated requirements. In determining whether to grant a certificate under this section, the commission shall examine the following factors:
(1) The following, which must be set forth in the energy utility's application for the certificate sought, in accordance with section 7(a) of this chapter:
(B) A description of the federally mandated costs associated with the compliance project, including costs that are allocated to the energy utility:
As added by P.L.150-2011, SEC.1. Amended by P.L.2-2023, SEC.4.