Ind. Code § 8-1-42-18
(a) Subject to subsection (b), and except as otherwise allowed by IC 36-7-4-1109 , a project owner may not install or locate a CSE system in a unit unless the project owner submits to the permit authority a decommissioning and site restoration plan, and posts a surety bond, or an equivalent means of security acceptable to the permit authority, including a parent company guarantee or an irrevocable letter of credit, but excluding cash, in an amount equal to the estimated cost of decommissioning the CSE system, as calculated by a third party licensed or registered engineer or by another person with suitable experience in the decommissioning of CSE systems, as agreed upon by the project owner and the permit authority. The required bond or other security shall be posted in increments such that the total amount of the bond or security posted is as follows:
(3) An amount equal to one hundred percent (100%) of the total estimated decommissioning costs not later than the tenth anniversary of the start date of the CSE system's full commercial operation. For purposes of this subdivision, the total estimated decommissioning costs shall be reevaluated by a third party licensed or registered engineer (or by another person with suitable experience in the decommissioning of CSE systems, as agreed upon by the project owner and the permit authority):
(B) at least once every succeeding five (5) year period after the tenth anniversary of the start date of the CSE system's full commercial operation;
and the total amount of the bond or security posted under this subdivision shall be adjusted as necessary after each reevaluation.
(c) A project owner shall provide to the permit authority written notice of the project owner's intent to decommission a CSE system not later than sixty (60) days before the discontinuation of commercial operation by the CSE system. Except as provided in subsection (e), after the discontinuation of commercial operation by the CSE system, and as part of the decommissioning process:
(d) Except as provided in subsection (e), if the project owner fails to remove all CSE system project assets not later than one (1) year after the proposed date of final decommissioning, as set forth in the notice to the permit authority under subsection (c), the permit authority may engage qualified contractors to:
(4) remediate the site;
and may initiate proceedings to recover any costs incurred.
(e) Project assets may remain in place after decommissioning is complete if:
As added by P.L.90-2022, SEC.2.