Ind. Code § 8-1-37-13
(a) The commission may establish a shareholder incentive consisting of the authorization of an increased overall rate of return on equity, not to exceed fifty (50) basis points over a participating electricity supplier's authorized rate of return, whenever the participating electricity supplier attains a CPS goal set forth in section 12(a) of this chapter. The number of additional basis points authorized by the commission under this subsection may:
(2) in the case of a particular participating electricity supplier, be based on the extent to which the participating electricity supplier met a particular CPS goal using clean energy resources listed in section 4(a)(1) through 4(a)(16) of this chapter.
The additional basis points authorized by the commission under this subsection for each CPS goal period are not cumulative. In determining a participating electricity supplier's authorized rate of return to which additional basis points may be added upon the participating electricity supplier's achievement of a particular CPS goal, the commission shall not include as part of the authorized rate of return any additional basis points awarded to the participating electricity supplier for having achieved the immediately preceding CPS goal.
(b) If the commission approves an electricity supplier's application under section 11(c) of this chapter, the commission shall authorize the incentive described in subsection (a) and the recovery of costs, by means of a periodic rate adjustment mechanism, as described in subsection (c), based on the following considerations:
(c) If the commission approved an electricity supplier's application under section 11(c) of this chapter, the commission shall permit the recovery, by means of a periodic rate adjustment mechanism, of all just, reasonable, and necessary program costs incurred by a participating electricity supplier in:
(1) constructing, operating, or maintaining facilities that generate clean energy that:
(2) otherwise generating or purchasing clean energy that is used by the participating electricity supplier in its efforts to meet a CPS goal set forth in section 12(a) of this chapter.
For purposes of this subsection and subsection (h)(1), "program costs" includes administrative costs, ancillary costs, capacity costs, costs associated with CECs, capital costs, depreciation costs, tax costs, and financing costs incurred in connection with an activity described in subdivision (1) or (2).
(2) not later than any dates specified by the commission in rules adopted under section 10 of this chapter;
for approval for the incentive or periodic rate adjustment mechanism sought.
(g) Subject to the participating electricity supplier's continuing compliance with the applicable CPS goal, as determined according to the measurement and evaluation procedures described in section 10(b)(1)(B) of this chapter, a shareholder incentive described in subsection (a) continues in effect until the earlier of the following:
(h) Subject to the participating electricity supplier's continuing compliance with the applicable CPS goal, as determined according to the measurement and evaluation procedures described in section 10(b)(1)(B) of this chapter, a periodic rate adjustment mechanism described in subsection (c) continues in effect until the earlier of the following:
As added by P.L.150-2011, SEC.16. Amended by P.L.83-2023, SEC.7.