Ind. Code § 8-1-32.3-15
(a) This chapter applies to permits issued by a permit authority to a communications service provider, under local law and consistent with IC 36-7 , for the following:
(b) A permit authority may not require an application or a permit for, or charge fees for, any of the following:
(2) The replacement of wireless facilities with wireless facilities that are:
(B) the same size or smaller than;
the wireless facilities being replaced.
(3) The installation, placement, maintenance, or replacement of micro wireless facilities that are suspended on cables strung between existing utility poles in compliance with applicable codes by a communications service provider that is authorized to use the public rights-of-way. For purposes of this subdivision, "applicable codes" means uniform building, fire, electrical, plumbing, or mechanical codes that are:
(B) enacted solely to address imminent threats of destruction of property or injury to persons;
including any local amendments to those codes.
(c) With respect to the construction, placement, or use of a small cell facility and the associated supporting structure, a permit authority may prohibit the placement of a new utility pole or a new wireless support structure in a right-of-way within an area that is designated strictly for underground or buried utilities, if all of the following apply:
(2) The permit authority does all of the following:
(A) Allows the collocation of small cell facilities on existing:
(ii) wireless support structures;
within the area.
(B) Allows the replacement or improvement of existing:
(ii) wireless support structures;
within the area.
(C) Provides:
(iii) another procedure;
that addresses requests to install new utility poles or new wireless support structures within the area.
(e) Subject to section 26(b) of this chapter, with respect to the construction, placement, or use of a small cell facility and the associated supporting structure within an area:
(3) that is subject to the jurisdiction of the Meridian Street preservation commission under IC 36-7-11.2 ;
a permit authority may apply any generally applicable procedures that require applicants to obtain a certificate of appropriateness.
(f) An applicant for the placement of a small cell facility and an associated supporting structure shall comply with applicable:
(2) industry standards;
for identifying the owner's name and contact information.
(g) A resolution, ordinance, or other regulation:
(2) that designates an area within the jurisdiction of the permit authority as strictly for underground or buried utilities;
applies only to communications service providers and those geographic areas that are zoned residential and where all existing utility infrastructure is already buried.
As added by P.L.145-2015, SEC.3. Amended by P.L.261-2017, SEC.8; P.L.23-2018, SEC.1.