- (a) When a petition is filed under section 8 of this chapter, the commission shall conduct a hearing.
(b) The office of the utility consumer counselor may:
(1) examine information of the eligible utility to confirm:
- (A) that the infrastructure improvements are in accordance with section 5 of this chapter; and
- (B) proper calculation of the adjustment amount proposed under section 8(a) of this chapter; and
- (2) submit a report to the commission not later than thirty (30) days after the petition is filed.
- (c) The commission shall hold the hearing and issue its order not later than sixty (60) days after the petition is filed.
- (d) If the commission finds that a petition filed under section 8 of this chapter complies with the requirements of this chapter, the commission shall enter an order approving the petition.
As added by P.L.94-2000, SEC.1. Amended by P.L.209-2014, SEC.10; P.L.212-2015, SEC.9; P.L.104-2016, SEC.2.