- (a) This section applies when a utility fails to follow the procedures provided in this chapter for withdrawal from or return to the commission's jurisdiction.
(b) To contest compliance with this chapter:
- (1) parties aggrieved by the decision to withdraw from commission jurisdiction; or
(2) other interested parties;
must file an action in the circuit or superior court with jurisdiction in the county where the utility has its principal office.
- (c) An action filed under this section must be filed not later than thirty (30) days after the date of the vote regarding commission jurisdiction over the utility.
As added by P.L.159-1999, SEC.17.