Ind. Code § 8-1-26-20
(a) In addition to the notice required in section 16 of this chapter, a person responsible for an excavation or demolition operation under section 14 of this chapter shall do all of the following:
(2) Maintain a clearance between an underground facility, as marked by the operator, and the cutting edge or point of mechanized equipment equal to the tolerance zone of the physical plant. If the clearance is less than two (2) feet, or if an underground facility is located or contained in or under pavement or another manmade hard surface, exposure of the underground facility may be accomplished only as follows:
(A) Only by the use of:
(B) Mechanized equipment may not be used within the tolerance zone of the physical plant unless the person responsible for the excavation or demolition does the following:
(C) Mechanized equipment may be used for the initial penetration and removal of pavement or other manmade hard surfaces if an underground facility is located or contained in or under pavement or another manmade hard surface, or if there is pavement or another manmade hard surface extending up to the tolerance zone of the physical plant, subject to the following:
(3) Notify the association if:
(b) A person who:
(2) causes damage to a pipeline facility in the area of the excavation or demolition;
may be subject to a civil penalty in an amount recommended by the advisory committee and approved by the commission, not to exceed ten thousand dollars ($10,000).
As added by P.L.69-1990, SEC.2. Amended by P.L.62-2009, SEC.17; P.L.200-2014, SEC.6; P.L.53-2024, SEC.10.