Ind. Code § 5-30-8-2

Replacement of subcontractor for primary design services and construction services

As added by P.L.74-2005, SEC.1.
  1. (a) A person identified under IC 5-30-7-1 (2) as a person with whom the design-builder proposes to enter into subcontracts for primary design services and primary construction services under the design-build contract may not be replaced without the approval of the public agency and a written determination by the public agency that a legitimate reason exists for the replacement.
  2. (b) If a design-builder violates subsection (a), the public agency may cancel the award of or may terminate a design-build contract.

As added by P.L.74-2005, SEC.1.