A unit shall provide an applicant with a schedule of the requirements for applying for and obtaining a permit, including the following:
(1) A list of any plan reviews or inspections that are required by the unit. The schedule must state that an applicant:
(A) may use:
- (i) the unit to conduct any plan review or inspection; or
- (ii) a private provider to conduct any plan review or inspection; and
- (B) must indicate on the application whether the applicant will use a private provider.
- (2) The timeline set forth in this chapter for notifications and submission of documents.
- (3) Any regulatory fees charged by the unit.
(4) All of the requirements for a complete application. The schedule must specify any documents that must accompany the application, including any prior approvals or permits for:
- (A) zoning;
- (B) drainage;
- (C) sewer or septic;
- (D) wells;
- (E) driveways; or
(F) flood control;
that the applicant must obtain before applying for the permit.
- (5) If a private provider is used to conduct a plan review or inspection, a copy of the private provider's certificate of insurance indicating that the private provider satisfies the coverage amounts set forth in section 26 of this chapter.
As added by P.L.146-2025, SEC.4.