Ind. Code § 32-28-3-1
(a) A contractor, a subcontractor, a mechanic, a lessor leasing construction and other equipment and tools, whether or not an operator is also provided by the lessor, a journeyman, a laborer, or any other person performing labor or furnishing materials or machinery, including the leasing of equipment or tools, for:
(1) the erection, alteration, repair, or removal of:
(3) any other earth moving operation;
may have a lien as set forth in this section.
(b) A person described in subsection (a) may have a lien separately or jointly:
(1) upon the house, mill, manufactory, or other building, bridge, reservoir, system of waterworks, or other structure, sidewalk, walk, stile, well, drain, drainage ditch, sewer, cistern, or earth:
(2) on the interest of the owner of the lot or parcel of land:
(B) with which the structure or improvement is connected;
to the extent of the value of any labor done or the material furnished, or both, including any use of the leased equipment and tools.
(c) All claims for wages of mechanics and laborers employed in or about a shop, mill, wareroom, storeroom, manufactory or structure, bridge, reservoir, system of waterworks or other structure, sidewalk, walk, stile, well, drain, drainage ditch, cistern, or any other earth moving operation shall be a lien on all the:
(5) finished or unfinished work;
located in or about the shop, mill, wareroom, storeroom, manufactory or other building, bridge, reservoir, system of waterworks, or other structure, sidewalk, walk, stile, well, drain, drainage ditch, sewer, cistern, or earth used in a business.
(e) Subject to subsection (f), a contract:
(3) for the construction, alteration, or repair of property that is:
(A) owned, operated, managed, or controlled by a:
(vi) not-for-profit utility (as defined in IC 8-1-2-125 );
regulated under IC 8 ; and
(4) to prepare property for Class 2 residential construction;
may include a provision or stipulation in the contract of the owner and principal contractor that a lien may not attach to the real estate, building, structure or any other improvement of the owner.
(f) A contract containing a provision or stipulation described in subsection (e) must meet the requirements of this subsection to be valid against subcontractors, mechanics, journeymen, laborers, or persons performing labor upon or furnishing materials or machinery for the property or improvement of the owner. The contract must:
(4) be filed and recorded in the recorder's office of the county in which the real estate, building, structure, or other improvement is situated not more than five (5) days after the date of execution of the contract.
A contract containing a provision or stipulation described in subsection
(g) Upon the filing of a contract under subsection (f), the recorder shall:
(2) index the contract in the name of the:
(B) owner;
in books kept for that purpose; and
(h) A person, firm, partnership, limited liability company, or corporation that sells or furnishes on credit any material, labor, or machinery for the alteration or repair of an owner occupied single or double family dwelling or the appurtenances or additions to the dwelling to:
(2) anyone other than the occupying owner or the owner's legal representative;
must furnish to the occupying owner of the parcel of land where the material, labor, or machinery is delivered a written notice of the delivery or work and of the existence of lien rights not later than thirty
(i) A person, firm, partnership, limited liability company, or corporation that sells or furnishes on credit material, labor, or machinery for the original construction of a single or double family dwelling for the intended occupancy of the owner upon whose real estate the construction takes place to a contractor, subcontractor, mechanic, or anyone other than the owner or the owner's legal representatives must:
(1) furnish the owner of the real estate:
(B) if IC 6-1.1-5-9 applies, as named in the transfer books of the township assessor (if any) or the county assessor;
with a written notice of the delivery or labor and the existence of lien rights not later than sixty (60) days after the date of the first delivery or labor performed; and
(2) file a copy of the written notice in the recorder's office of the county not later than sixty (60) days after the date of the first delivery or labor performed.
The furnishing and filing of the notice is a condition precedent to the right of acquiring a lien upon the real estate or upon the improvement constructed on the real estate.
(j) A lien for material or labor in original construction does not attach to real estate purchased by an innocent purchaser for value without notice of a single or double family dwelling for occupancy by the purchaser unless notice of intention to hold the lien is recorded under section 3 of this chapter before recording the deed by which the purchaser takes title.
[Pre-2002 Recodification Citation: 32-8-3-1.]
As added by P.L.2-2002, SEC.13. Amended by P.L.101-2002, SEC.5; P.L.151-2003, SEC.1; P.L.1-2006, SEC.501; P.L.1-2007, SEC.210; P.L.219-2007, SEC.101; P.L.146-2008, SEC.674; P.L.81-2020, SEC.18.