Ind. Code § 13-15-4-16
(b) Subject to subsection (c), the commissioner shall:
(2) deny;
the draft permit not later than twenty-five (25) business days after receiving the draft permit.
(c) If notice of opportunity for public comment or public hearing is required under applicable law before a permit decision can be issued, the commissioner shall comply with all public participation requirements and:
(2) deny;
the draft permit not later than fifty-five (55) business days after receipt of the draft permit.
(e) If an applicant has elected to have a draft permit prepared under section 11(b)(2) of this chapter and:
(2) the commissioner fails to approve or deny the draft permit;
within the applicable time specified under subsection (a), (b), or (c), the department shall refund the applicant's permit application fee not later than twenty-five (25) business days after expiration of the applicable period.
(f) The commissioner and the applicant may mutually agree to extend the deadlines in this section.
[Pre-1996 Recodification Citation: 13-7-10.1-10.]
As added by P.L.1-1996, SEC.5. Amended by P.L.184-2002, SEC.9; P.L.135-2026, SEC.123.