Rule 672-21-.02. Eligibility for Filing Bid Protest
(1) The following Bidders may file a Bid Protest:
- a. a Bidder who has not been identified as the Apparent Low Bidder for a Construction Project and where its bid is in an amount lower than that of the Apparent Low Bidder; or
- b. an Apparent Low Bidder that has not been awarded the Construction Project.
(2) No Bidder may file a Bid Protest when:
- a. all bids have been rejected by the Department for the subject federally funded Construction Project; or
- b. the Department determines in its sole discretion that any and all Bid Protests are barred as a result of an imminent or serious danger to the public health, safety, or welfare or to property that requires the immediate awarding of the Construction Project.
- (3) Failure to timely file a Bid Protest pursuant to this Chapter constitutes a waiver of the right to file a Bid Protest.
- (4) Failure to include the information and documentation required by this Chapter with a Bid Protest constitutes a waiver of the right to file a Bid Protest.
- (5) Completion of the Bid Protest procedures described in this Chapter is a condition precedent to the commencement of any legal or equitable action.
Authority: O.C.G.A. §§ 32-2-69, 50-13-4.
History. Original Rule entitled "Eligibility for Filing Bid Protest" adopted. F. Nov. 19, 2020; eff. Dec. 9, 2020.