Fla. Admin. Code R. 25-6.0423
(2) Definitions. As used in this rule, the following definitions shall apply:
(6) Pre-Construction Costs and Carrying Costs on Construction Cost Balance. After the Commission has issued a final order granting a determination of need for a power plant pursuant to Section 403.519, F.S., a utility may petition the Commission for recovery of pre-construction costs and carrying costs of construction cost balance as follows:
(c) Cost Recovery for Nuclear or Integrated Gasification Combined Cycle Power Plant Costs.
1. Each year, pursuant to the order establishing procedure in the annual cost recovery proceeding, a utility shall submit for Commission review and approval, as part of its cost recovery filings:
a. True-Up for Previous Years. A utility shall submit its final true-up of pre-construction expenditures, based on actual preconstruction expenditures for the prior year and previously filed expenditures for such prior year and a description of the pre-construction work actually performed during such year; or, once construction begins, its final true-up of carrying costs on its construction expenditures, based on actual carrying costs on construction expenditures for the prior year and previously filed carrying costs on construction expenditures for such prior year and a description of the construction work actually performed during such year.
b. True-Up and Projections for Current Year. A utility shall submit for Commission review and approval its actual/estimated true-up of projected pre-construction expenditures based on a comparison of current year actual/estimated expenditures and the previously-filed estimated expenditures for such current year and a description of the pre-construction work projected to be performed during such year; or, once construction begins, its actual/estimated true-up of projected carrying costs on construction expenditures based on a comparison of current year actual/estimated carrying costs on construction expenditures and the previously filed estimated carrying costs on construction expenditures for such current year and a description of the construction work projected to be performed during such year.
c. Projected Costs for Subsequent Years. A utility shall submit, for Commission review and approval, its projected pre-construction expenditures for the subsequent year and a description of the pre-construction work projected to be performed during such year; or, once construction begins, its projected construction expenditures for the subsequent year and a description of the construction work projected to be performed during such year.
2. The Commission shall conduct an annual hearing to determine the reasonableness of projected pre-construction expenditures and prudence of actual pre-construction expenditures expended by the utility; or, once construction begins, to determine the reasonableness of projected construction expenditures and prudence of actual construction expenditures expended by the utility, and the associated carrying costs. The Commission shall conduct an on-going auditing and monitoring program of prior year actual construction costs and related contracts pursuant to Section 366.08, F.S. In making its determination of reasonableness and prudence the Commission shall apply the standard provided pursuant to Section 403.519(4)(e), F.S.
3. Upon a determination of prudence, prior year actual costs associated with power plant construction subject to the annual proceeding shall not be subject to disallowance or further prudence review.
4. The final true-up for the previous year, actual/estimated true-up for the current year, and subsequent year’s projected power plant costs as approved by the Commission pursuant to subparagraph (6)(c)2. will be included for cost recovery purposes as a component of the following year’s capacity cost recovery factor in the Fuel and Purchased Power Cost Recovery Clause. The utility must file all necessary revisions to the fuel and purchased power cost recovery filings no later than eight business days after the Commission’s vote.
5. Along with the filings required by this paragraph, each year a utility shall submit for Commission review and approval a detailed analysis of the long-term feasibility of completing the power plant. Such analysis shall include evidence that the utility intends to construct the nuclear or integrated gasification combined cycle power plant by showing that it has committed sufficient, meaningful, and available resources to enable the project to be completed and that its intent is realistic and practical.
(7) Failure to Enter Commercial Service. Following the Commission’s issuance of a final order granting a determination of need for the power plant, in the event the utility elects not to complete or is precluded from completing construction of the power plant, the utility shall be allowed to recover all prudent site selection costs, pre-construction costs, and construction costs.
(8) Commercial Service. As operating units or systems associated with the power plant and the power plant itself are placed in commercial service:
(9) A utility shall, contemporaneously with the filings required by paragraph (6)(c) above, file a detailed statement of project costs sufficient to support a Commission determination of prudence, including, but not limited to, the information required in paragraphs (9)(b) – (9)(e), below.
Rulemaking Authority 350.127(2), 366.05(1), 366.93(2) FS. Law Implemented 366.93 FS. History–New 4-8-07, Amended 2-3-08, 1-29-14.